Home
Class 12
MATHS
9 men finish one-third work in 10 days. ...

9 men finish one-third work in 10 days. The number of additional men required for finishing the remaining work in 2 more days will be

A

78

B

81

C

55

D

30

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these calculations: ### Step 1: Determine the total work done by 9 men in 10 days. Given that 9 men finish one-third of the work in 10 days, we can denote the total work as W. - Work done in 10 days = \( \frac{1}{3}W \) ### Step 2: Calculate the total work (W). If 9 men complete \( \frac{1}{3}W \) in 10 days, we can find the total work W as follows: - Total work \( W = 3 \times \frac{1}{3}W = W \) ### Step 3: Find the work done by one man in one day. To find out how much work one man can do in one day, we can use the following formula: - Work done by 9 men in 10 days = \( \frac{1}{3}W \) - Work done by 1 man in 10 days = \( \frac{1}{3}W \div 9 = \frac{1}{27}W \) - Work done by 1 man in 1 day = \( \frac{1}{27}W \div 10 = \frac{1}{270}W \) ### Step 4: Calculate the remaining work. Since one-third of the work is completed, the remaining work is: - Remaining work = \( W - \frac{1}{3}W = \frac{2}{3}W \) ### Step 5: Determine how many men are needed to finish the remaining work in 2 days. Let M be the number of men required to finish the remaining work in 2 days. The total work done by M men in 2 days can be expressed as: - Work done by M men in 2 days = \( M \times \text{(work done by 1 man in 1 day)} \times 2 \) - Work done by M men in 2 days = \( M \times \frac{1}{270}W \times 2 = \frac{2M}{270}W = \frac{M}{135}W \) ### Step 6: Set up the equation for the remaining work. To finish the remaining work \( \frac{2}{3}W \) in 2 days, we set up the equation: \[ \frac{M}{135}W = \frac{2}{3}W \] ### Step 7: Solve for M. We can cancel W from both sides (assuming W ≠ 0): \[ \frac{M}{135} = \frac{2}{3} \] Now, cross-multiply to solve for M: \[ M = 135 \times \frac{2}{3} = 90 \] ### Step 8: Calculate the additional men required. We already have 9 men working, so the additional men required will be: \[ \text{Additional men} = M - 9 = 90 - 9 = 81 \] ### Final Answer: The number of additional men required to finish the remaining work in 2 more days is **81**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT PUBLICATION JHARKHAND|Exercise Exam Booster for Cracking Exam |18 Videos
  • TIME AND DISTANCE

    ARIHANT PUBLICATION JHARKHAND|Exercise Exam Booster for Cracking Exam |25 Videos
  • TRIGNOMETRIC RATIOS

    ARIHANT PUBLICATION JHARKHAND|Exercise Exam Booster for Cracking Exam|25 Videos

Similar Questions

Explore conceptually related problems

16 men finished one-third work in 6 days. The number of additional men are required to complete the remaining job in next 6 days:

24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:

12 men finished frac(1)(4)th part of whole work in 6 days. Find the number of additional men required to complete the job innext 6 days.

16 men can finish a piece of work in 49 days.14 men started working and in 8 days they could finish certain amount of work.If it is required to finish the remaining work.in 24 days.How many more men should be added to the existing workforce? 21 b.28 c.16 d.14

P and Q can finish a work in 30 days. They worked at it for 10 days and then Q left. The remaining work is done byPalone in 20 more days. How long willPtake to finish the work alone?

ARIHANT PUBLICATION JHARKHAND-TIME AND WORK-Exam Booster for Cracking Exam
  1. A can do a piece of work in 24 days. If B is 60% more efficient than A...

    Text Solution

    |

  2. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  3. A cistern which has a leak in the bottom is filled in 15 h. Had there ...

    Text Solution

    |

  4. 24 men can complete a job in 40 days. The number men required to compl...

    Text Solution

    |

  5. A can finish a work in 12 days and B can do it in 15 days. ’After A ha...

    Text Solution

    |

  6. If a work can be completed by A in 30 days and by B in 60 days. Then, ...

    Text Solution

    |

  7. If x men can do a work in z days. Then, the number of days taken by (x...

    Text Solution

    |

  8. A and B can complete a task in 30 days when working together after A a...

    Text Solution

    |

  9. 9 men finish one-third work in 10 days. The number of additional men r...

    Text Solution

    |

  10. Ravi alone does a piece of work in 2 days and Rajesh does it in 6 days...

    Text Solution

    |

  11. X can do 3/4 of a work in 12 days. In how many days X can finish the 1...

    Text Solution

    |

  12. Ravi can build a wall in the same time in which Mahesh and Suresh toge...

    Text Solution

    |

  13. Sita can do a work in 15 days and Gita can do it in 25 days and Meera ...

    Text Solution

    |

  14. 7 men and 8 boys can do a piece of work in 2 days. 4 men and 12 boys c...

    Text Solution

    |

  15. 2 men undertake to do a job for 1400. One can do it alone in 7 days an...

    Text Solution

    |

  16. A group of workers engaged in plastering a wall, completed half of the...

    Text Solution

    |

  17. A can do a piece of work in 9 days, B in 12 days and C in 15 days. The...

    Text Solution

    |

  18. A, B and C are three taps in a tank. Taps A and B can fill the tank in...

    Text Solution

    |