Home
Class 12
MATHS
7 men and 8 boys can do a piece of work ...

7 men and 8 boys can do a piece of work in 2 days. 4 men and 12 boys can do 29/56 of the same work in 1 day, in how many days will 1 man do this work?

A

28 days

B

26 days

C

50 days

D

None of these

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will define the work done by men and boys, set up equations based on the information given, and then solve for the number of days it takes for one man to complete the work. ### Step 1: Define Variables Let: - \( M \) = work done by 1 man in 1 day - \( B \) = work done by 1 boy in 1 day ### Step 2: Set Up the First Equation From the problem, we know that 7 men and 8 boys can complete the work in 2 days. Therefore, the total work can be expressed as: \[ 7M + 8B = \frac{1}{2} \quad \text{(since they complete 1 part in 2 days)} \] This simplifies to: \[ 7M + 8B = \frac{1}{2} \] ### Step 3: Set Up the Second Equation Next, we know that 4 men and 12 boys can complete \( \frac{29}{56} \) of the work in 1 day. Thus, we can write: \[ 4M + 12B = \frac{29}{56} \] ### Step 4: Solve the Equations We now have two equations: 1. \( 7M + 8B = \frac{1}{2} \) (Equation 1) 2. \( 4M + 12B = \frac{29}{56} \) (Equation 2) To eliminate one variable, we can multiply Equation 1 by 3 and Equation 2 by 2: \[ 3(7M + 8B) = 3 \cdot \frac{1}{2} \implies 21M + 24B = \frac{3}{2} \quad \text{(Equation 3)} \] \[ 2(4M + 12B) = 2 \cdot \frac{29}{56} \implies 8M + 24B = \frac{29}{28} \quad \text{(Equation 4)} \] ### Step 5: Subtract the Equations Now, we subtract Equation 4 from Equation 3: \[ (21M + 24B) - (8M + 24B) = \frac{3}{2} - \frac{29}{28} \] This simplifies to: \[ 13M = \frac{3}{2} - \frac{29}{28} \] ### Step 6: Find a Common Denominator To subtract the fractions, we find a common denominator: \[ \frac{3}{2} = \frac{42}{28} \quad \text{(converting to a common denominator)} \] Thus: \[ \frac{3}{2} - \frac{29}{28} = \frac{42}{28} - \frac{29}{28} = \frac{13}{28} \] ### Step 7: Solve for M Now we have: \[ 13M = \frac{13}{28} \] Dividing both sides by 13 gives: \[ M = \frac{1}{28} \] ### Step 8: Calculate the Days for 1 Man to Complete the Work Since 1 man can do \( \frac{1}{28} \) of the work in one day, the number of days for 1 man to complete the whole work is: \[ \text{Days} = \frac{1}{M} = \frac{1}{\frac{1}{28}} = 28 \text{ days} \] ### Final Answer Thus, 1 man will take **28 days** to complete the work. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT PUBLICATION JHARKHAND|Exercise Exam Booster for Cracking Exam |18 Videos
  • TIME AND DISTANCE

    ARIHANT PUBLICATION JHARKHAND|Exercise Exam Booster for Cracking Exam |25 Videos
  • TRIGNOMETRIC RATIOS

    ARIHANT PUBLICATION JHARKHAND|Exercise Exam Booster for Cracking Exam|25 Videos

Similar Questions

Explore conceptually related problems

If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in

2men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days.In how many days can 2 men and 1 boy do the work?

2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?

While 4 men and 6 boys can do a piece of work in 2 days, 1 man, and 3 boys can do the same work in 6 days. In how many days can 1 man and 1 boy complete the same work?

If 2 men and 7 boys do a piece of work in 14 days while 3 men and 8 boys do the same piece of work in 11 days, then in how many days will 8 men and 6 boys do thrice of that work? (A) 11 (B) 21 (C) 31 (D) 41

If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the same work in 6 days, how long will 6 men and 24 boys take to complete the same work?

12 men and 16 boys can do a piece of work in 5 days. 13 men and 24 boys can do the same work in 4 days. How long will 7 men and 10 boys take to do the same work?

ARIHANT PUBLICATION JHARKHAND-TIME AND WORK-Exam Booster for Cracking Exam
  1. A can do a piece of work in 24 days. If B is 60% more efficient than A...

    Text Solution

    |

  2. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  3. A cistern which has a leak in the bottom is filled in 15 h. Had there ...

    Text Solution

    |

  4. 24 men can complete a job in 40 days. The number men required to compl...

    Text Solution

    |

  5. A can finish a work in 12 days and B can do it in 15 days. ’After A ha...

    Text Solution

    |

  6. If a work can be completed by A in 30 days and by B in 60 days. Then, ...

    Text Solution

    |

  7. If x men can do a work in z days. Then, the number of days taken by (x...

    Text Solution

    |

  8. A and B can complete a task in 30 days when working together after A a...

    Text Solution

    |

  9. 9 men finish one-third work in 10 days. The number of additional men r...

    Text Solution

    |

  10. Ravi alone does a piece of work in 2 days and Rajesh does it in 6 days...

    Text Solution

    |

  11. X can do 3/4 of a work in 12 days. In how many days X can finish the 1...

    Text Solution

    |

  12. Ravi can build a wall in the same time in which Mahesh and Suresh toge...

    Text Solution

    |

  13. Sita can do a work in 15 days and Gita can do it in 25 days and Meera ...

    Text Solution

    |

  14. 7 men and 8 boys can do a piece of work in 2 days. 4 men and 12 boys c...

    Text Solution

    |

  15. 2 men undertake to do a job for 1400. One can do it alone in 7 days an...

    Text Solution

    |

  16. A group of workers engaged in plastering a wall, completed half of the...

    Text Solution

    |

  17. A can do a piece of work in 9 days, B in 12 days and C in 15 days. The...

    Text Solution

    |

  18. A, B and C are three taps in a tank. Taps A and B can fill the tank in...

    Text Solution

    |