Home
Class 14
MATHS
A and B together can do a piece of work ...

A and B together can do a piece of work in 12 days which B and C together can do in 16 days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In how many days B could finish the work?
A और B मिलकर एक काम 12 दिन में कर सकते हैं जसे B और C मिलकर 16 दिन में कर सकते हैं। A द्वारा उस पर 5 दिन और B द्वारा 7 दिन करने के बाद C ने उसे 13 दिन में पूरा कर दिया। B उस काम को कितने दिन में पूरा कर सकता था? Options are (a) 48 day/ 48 दिन (b)24 day/ 24 दिन (c)16 day/ 16 दिन (d)12 day/ 12 दिन

A

48 day/ 48 दिन

B

24 day/ 24 दिन

C

16 day/ 16 दिन

D

12 day/ 12 दिन

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to find out how many days B can finish the work alone. Let's break it down step by step. ### Step 1: Determine the work rates of A, B, and C 1. **A and B's work rate**: A and B together can complete the work in 12 days. Therefore, their combined work rate is: \[ \text{Work rate of A + B} = \frac{1}{12} \text{ (work per day)} \] 2. **B and C's work rate**: B and C together can complete the work in 16 days. Therefore, their combined work rate is: \[ \text{Work rate of B + C} = \frac{1}{16} \text{ (work per day)} \] ### Step 2: Set up equations for individual work rates Let: - A's work rate = \( a \) - B's work rate = \( b \) - C's work rate = \( c \) From the above information, we can write the following equations: 1. \( a + b = \frac{1}{12} \) (1) 2. \( b + c = \frac{1}{16} \) (2) ### Step 3: Work done by A, B, and C Now, we know: - A works for 5 days, so the work done by A is: \[ \text{Work done by A} = 5a \] - B works for 7 days, so the work done by B is: \[ \text{Work done by B} = 7b \] - C finishes the remaining work in 13 days, so the work done by C is: \[ \text{Work done by C} = 13c \] ### Step 4: Total work equation The total work done by A, B, and C together should equal 1 (the whole work): \[ 5a + 7b + 13c = 1 \quad \text{(3)} \] ### Step 5: Substitute for c From equation (2), we can express \( c \) in terms of \( b \): \[ c = \frac{1}{16} - b \] ### Step 6: Substitute c into equation (3) Substituting \( c \) into equation (3): \[ 5a + 7b + 13\left(\frac{1}{16} - b\right) = 1 \] Expanding this gives: \[ 5a + 7b + \frac{13}{16} - 13b = 1 \] Combining like terms: \[ 5a - 6b + \frac{13}{16} = 1 \] Rearranging gives: \[ 5a - 6b = 1 - \frac{13}{16} = \frac{3}{16} \quad \text{(4)} \] ### Step 7: Solve the system of equations Now we have two equations: 1. \( a + b = \frac{1}{12} \) (1) 2. \( 5a - 6b = \frac{3}{16} \) (4) From equation (1), we can express \( a \): \[ a = \frac{1}{12} - b \] Substituting this into equation (4): \[ 5\left(\frac{1}{12} - b\right) - 6b = \frac{3}{16} \] Expanding gives: \[ \frac{5}{12} - 5b - 6b = \frac{3}{16} \] Combining terms: \[ \frac{5}{12} - 11b = \frac{3}{16} \] Now, convert \( \frac{5}{12} \) to a fraction with a denominator of 48: \[ \frac{5}{12} = \frac{20}{48}, \quad \frac{3}{16} = \frac{9}{48} \] So, we have: \[ \frac{20}{48} - 11b = \frac{9}{48} \] Rearranging gives: \[ 11b = \frac{20}{48} - \frac{9}{48} = \frac{11}{48} \] Thus: \[ b = \frac{11}{48 \times 11} = \frac{1}{48} \] ### Step 8: Calculate the days B can finish the work Since \( b \) is the work rate of B, the number of days B can finish the work alone is: \[ \text{Days for B} = \frac{1}{b} = 48 \text{ days} \] ### Final Answer B can finish the work in **48 days**.

To solve the problem, we need to find out how many days B can finish the work alone. Let's break it down step by step. ### Step 1: Determine the work rates of A, B, and C 1. **A and B's work rate**: A and B together can complete the work in 12 days. Therefore, their combined work rate is: \[ \text{Work rate of A + B} = \frac{1}{12} \text{ (work per day)} \] ...
Promotional Banner