A can do a work in 12 days and B can do ...

A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

A

6

B

5

C

7

D

`7.2`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how many days A and B worked together before A leaves 3 days before the work is completed. Here’s a step-by-step solution: ### Step 1: Determine the total work A can complete the work in 12 days, and B can complete it in 18 days. To find the total work, we can use the least common multiple (LCM) of the two times. **Calculation:** - LCM of 12 and 18 is 36. **Hint:** The LCM gives us a common measure of total work that both A and B can complete. ### Step 2: Calculate the work done by A and B in one day Now, we calculate how much work A and B can do in one day. **Calculation:** - Work done by A in one day = Total work / Days taken by A = 36 / 12 = 3 - Work done by B in one day = Total work / Days taken by B = 36 / 18 = 2 **Hint:** The work done in one day is found by dividing the total work by the number of days each person takes to complete the work. ### Step 3: Calculate the total work done by B alone in the last 3 days Since A leaves 3 days before the work is completed, we need to calculate how much work B does alone in those 3 days. **Calculation:** - Work done by B in 3 days = Work done by B in one day × 3 = 2 × 3 = 6 **Hint:** To find the work done by one person over multiple days, multiply the daily work by the number of days. ### Step 4: Calculate the remaining work after B's contribution Now, we need to find out how much work was done by A and B together before A left. **Calculation:** - Total work = 36 - Work done by B in the last 3 days = 6 - Remaining work done by A and B together = Total work - Work done by B = 36 - 6 = 30 **Hint:** Subtract the work done by B alone from the total work to find out how much work was completed while A was still present. ### Step 5: Calculate the total work done together in one day Now, we calculate how much work A and B do together in one day. **Calculation:** - Total work done together in one day = Work done by A + Work done by B = 3 + 2 = 5 **Hint:** The combined daily work rate is the sum of the individual daily work rates. ### Step 6: Calculate the number of days they worked together Finally, we can find out how many days A and B worked together by dividing the remaining work by their combined daily work. **Calculation:** - Days worked together = Remaining work / Combined daily work = 30 / 5 = 6 **Hint:** To find the number of days worked together, divide the remaining work by the total work done together in one day. ### Conclusion A and B worked together for **6 days**.
Promotional Banner