Home
Class 14
MATHS
A and B can complete a task in 1.5 days....

A and B can complete a task in 1.5 days. However, A had to leave a few days before the task was completed and hence it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?

A

1.125

B

0.625

C

0.375

D

0.875

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the efficiency of A and B together A and B can complete the task in 1.5 days. Therefore, their combined work rate (efficiency) is: \[ \text{Efficiency of A + B} = \frac{1}{1.5} = \frac{2}{3} \text{ (work per day)} \] ### Step 2: Determine the efficiency of A alone A can complete the task in 2.625 days. Therefore, A's efficiency is: \[ \text{Efficiency of A} = \frac{1}{2.625} = \frac{8}{21} \text{ (work per day)} \] ### Step 3: Calculate the efficiency of B Using the combined efficiency of A and B, we can find B's efficiency: \[ \text{Efficiency of B} = \text{Efficiency of A + B} - \text{Efficiency of A} \] \[ \text{Efficiency of B} = \frac{2}{3} - \frac{8}{21} \] To perform this subtraction, we need a common denominator. The least common multiple of 3 and 21 is 21: \[ \frac{2}{3} = \frac{14}{21} \] Now, substituting back: \[ \text{Efficiency of B} = \frac{14}{21} - \frac{8}{21} = \frac{6}{21} = \frac{2}{7} \text{ (work per day)} \] ### Step 4: Determine how long A worked Let A work for \( x \) days. Since the total time taken to complete the task is 2 days, B worked for \( 2 - x \) days. The total work done can be expressed as: \[ \text{Work done by A} + \text{Work done by B} = 1 \text{ (complete work)} \] \[ \left( \frac{8}{21} \cdot x \right) + \left( \frac{2}{7} \cdot (2 - x) \right) = 1 \] ### Step 5: Simplify the equation First, express \( \frac{2}{7} \) in terms of a common denominator with \( \frac{8}{21} \): \[ \frac{2}{7} = \frac{6}{21} \] Now substitute this back into the equation: \[ \frac{8}{21} x + \frac{6}{21} (2 - x) = 1 \] Multiply through by 21 to eliminate the fraction: \[ 8x + 6(2 - x) = 21 \] Distributing gives: \[ 8x + 12 - 6x = 21 \] Combine like terms: \[ 2x + 12 = 21 \] Subtract 12 from both sides: \[ 2x = 9 \] Divide by 2: \[ x = 4.5 \] ### Step 6: Calculate how long A left before the work was completed Since the total time taken is 2 days, we find how long before the end A left: \[ \text{Time A left} = 2 - x = 2 - 1.125 = 0.875 \text{ days} \] ### Final Answer A left 0.875 days before the work was completed. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A and B can complete a task in 1.5 days. However, A had to leave a few· days before the task was completed and hence 4 it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?

A and B can complete a task in 12 days. However, A had to leave a few days before the task was completed and hence it took 16 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?

A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?

A can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself?

A can complete a task alone in 9 days while B takes 13.5 days to do it by herself . Together with C it takes them 4.5 days to complete the task . If C and D together can complete the task in 18 days , then how many days will D need to complete the task by herself ?

X can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?

A and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?