Home
Class 14
MATHS
A, B, and C can alone do a task in 40, 1...

A, B, and C can alone do a task in 40, 120 and 36 days, respectively. A and B together work for 20 days and leave the task incomplete. C resumes it an complete it alone. How many days did C take to complete it?

A

A. 12

B

B. 20

C

C. 16

D

D. 18

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how long it takes for C to complete the remaining work after A and B have worked together for 20 days. Here’s a step-by-step breakdown: ### Step 1: Determine the work rates of A, B, and C - A can complete the task in 40 days, so A's work rate is \( \frac{1}{40} \) of the work per day. - B can complete the task in 120 days, so B's work rate is \( \frac{1}{120} \) of the work per day. - C can complete the task in 36 days, so C's work rate is \( \frac{1}{36} \) of the work per day. ### Step 2: Calculate the combined work rate of A and B To find the combined work rate of A and B, we add their individual work rates: \[ \text{Work rate of A and B} = \frac{1}{40} + \frac{1}{120} \] To add these fractions, we need a common denominator. The least common multiple (LCM) of 40 and 120 is 120. \[ \frac{1}{40} = \frac{3}{120} \quad \text{and} \quad \frac{1}{120} = \frac{1}{120} \] So, \[ \text{Combined work rate} = \frac{3}{120} + \frac{1}{120} = \frac{4}{120} = \frac{1}{30} \] This means A and B together can complete \( \frac{1}{30} \) of the work in one day. ### Step 3: Calculate the work done by A and B in 20 days Now, we calculate how much work A and B can complete in 20 days: \[ \text{Work done in 20 days} = 20 \times \frac{1}{30} = \frac{20}{30} = \frac{2}{3} \] Thus, A and B together complete \( \frac{2}{3} \) of the work in 20 days. ### Step 4: Determine the remaining work The total work is considered as 1 (the whole task). Therefore, the remaining work after A and B have worked is: \[ \text{Remaining work} = 1 - \frac{2}{3} = \frac{1}{3} \] ### Step 5: Calculate the time taken by C to complete the remaining work Now we need to find out how long it will take for C to complete the remaining \( \frac{1}{3} \) of the work. Since C's work rate is \( \frac{1}{36} \) of the work per day, we can set up the equation: \[ \text{Time taken by C} = \frac{\text{Remaining work}}{\text{Work rate of C}} = \frac{\frac{1}{3}}{\frac{1}{36}} = \frac{1}{3} \times 36 = 12 \text{ days} \] ### Final Answer C takes **12 days** to complete the remaining work. ---
Promotional Banner