30 men can complete a job in 40 days. Ho...

30 men can complete a job in 40 days. However, after 24 days some men out of the assigned 30 left the job. The remaining people took another 40 days to complete the job. The number of men who left the job is

A

24

B

18

C

12

D

6

Text Solution

Verified by Experts

Promotional Banner

Similar Questions

Explore conceptually related problems

5 men can complete a job in 8 days. How many days will it take if 12 men do the job?

22 men can complete a job in 16days. In how many days, will 32 men complete that job?

24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

If 40 men can complete a job in 6 days, then find the number fo days taken by 60 men to complete it.

If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?

If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?

If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?

24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :

40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in