Class 12
MATHS
A and B can do a piece of wok in 72 days...

A and B can do a piece of wok in 72 days, B and C can do it in 120 days, A and C can do it in 90 days. In what time can A alone do it ?

A

55 days

B

120 days

C

110 days

D

60 days

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT PUBLICATION BIHAR|Exercise Exam Booster for Cracking Exam |18 Videos
  • TIME AND DISTANCE

    ARIHANT PUBLICATION BIHAR|Exercise Exam Booster for Cracking Exam|25 Videos
  • TRIGONOMETRIC IDENTITIES

    ARIHANT PUBLICATION BIHAR|Exercise EXAM BOOSTER (FOR CRACKING EXAM)|35 Videos

Similar Questions

Explore conceptually related problems

A and B can do a piece of work in 72 days, B and C can do it in 120 days while A and C can do it in 90 days. In what time can A alone do it?

A and B can do a piece of work in 72 days B and C can do it in 120 days. A and C can do it in 90 days. In how many days, all the three together can do the work?

A and B can do a piece of work in 72 days,B and C can do it in 120 days,and A and C can do it in 90 days.When A,B and C work together,how much work is finished by them in 3days.

X and Y can do a piece of work in 72 days. Y and Z can do it in 120 days. X and Z can do it in 90 days. In how many days all the three together can do the work ? A)100 days B)150 days C)60 days D) 80 days

A and B can do a piece of work in 10 days.B and C can do it in 12 days. A and C can do it in 15 days. How long will A take to do it alone?

A and B can do a piece of work in 9 days; B and C can do it in 12 days; A and C can do it in 18 days.In how many days will A,B and C finish it working together and separately?

A and B can do a piece of work in 8 days. B and C can do it in 24 days, while C and A can do it in 8 4/7 days. In how many days can C do it alone?

A and B can do a piece of work in S days. B and C can do it in 24 days while C and A can do it in 8(4/7) days. In how many days can C do it alone?

A and B can do a piece of work in 5 days, B and C can do it in 7 days , A and C can do it in 4 days. Who among these will take the least time if put to do it alone ?

A and B can do a piece of work in 5 days; B and C can do it in 7 days; A and C can do it in 4 days. Who among these will take the least time if put do it alone ? a. A b. B c. C d. data inadequate

ARIHANT PUBLICATION BIHAR-TIME AND WORK-Exam Booster for Cracking Exam
  1. A and B can do a piece of wok in 72 days, B and C can do it in 120 day...

    Text Solution

    |

  2. A can do a piece of work in 24 days. If B is 60% more efficient than A...

    Text Solution

    |

  3. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  4. A cistern which has a leak in the bottom is filled in 15 h. Had there ...

    Text Solution

    |

  5. 24 men can complete a job in 40 days. The number men required to compl...

    Text Solution

    |

  6. A can finish a work in 12 days and B can do it in 15 days. ’After A ha...

    Text Solution

    |

  7. If a work can be completed by A in 30 days and by B in 60 days. Then, ...

    Text Solution

    |

  8. If x men can do a work in z days. Then, the number of days taken by (x...

    Text Solution

    |

  9. A and B can complete a task in 30 days when working together after A a...

    Text Solution

    |

  10. 9 men finish one-third work in 10 days. The number of additional men r...

    Text Solution

    |

  11. Ravi alone does a piece of work in 2 days and Rajesh does it in 6 days...

    Text Solution

    |

  12. X can do 3/4 of a work in 12 days. In how many days X can finish the 1...

    Text Solution

    |

  13. Ravi can build a wall in the same time in which Mahesh and Suresh toge...

    Text Solution

    |

  14. Sita can do a work in 15 days and Gita can do it in 25 days and Meera ...

    Text Solution

    |

  15. 7 men and 8 boys can do a piece of work in 2 days. 4 men and 12 boys c...

    Text Solution

    |

  16. 2 men undertake to do a job for 1400. One can do it alone in 7 days an...

    Text Solution

    |

  17. A group of workers engaged in plastering a wall, completed half of the...

    Text Solution

    |

  18. A can do a piece of work in 9 days, B in 12 days and C in 15 days. The...

    Text Solution

    |

  19. A, B and C are three taps in a tank. Taps A and B can fill the tank in...

    Text Solution

    |