A can complete a work in 10 days and B ...

A can complete a work in 10 days and B can in 15 days. B starts the work and is joined by A after 5 days. If they earn a total of Y 65, what are their individual shares?

A

₹ 24,₹ 41

B

₹ 30,₹ 35

C

₹ 20,₹ 45

D

₹ 25,₹ 40

Text Solution

Verified by Experts

Promotional Banner

Similar Questions

Explore conceptually related problems

A and B can complete a piece of work in 10 and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of ₹60, what are their individual shares ?

A and B can complete a piece of work in 10 and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of ₹60, what are their individual shares ?

A can do a piece of work in 18 days, B in36 days and C in 54 days. A starts the work and is joined by B after 1 day, C joins them after 4 more days. How many more days will be required to complete the work?

A can do a piece of work in 18 days, B in36 days and C in 54 days. A starts the work and is joined by B after 1 day, C joins them after 4 more days. How many more days will be required to complete the work?

A can do a work in 10 days and that of B in 15 days . B starts the work alone but after 3 days he left the work & A joined the work . In how many days will the total work be finished ?

A alone can do a certain job in 15 days , while B alone can do it in 10 days . A started the work and was joined by B after 5 days. The work lasted for how many days?