Home
Class 14
MATHS
7 men can complete a piece of work in 12...

7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

A

28

B

21

C

14 cm

D

7

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Similar Questions

Explore conceptually related problems

7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

On working 10 hourse a day, 15 men can complete a piece of work in 20 days. In how many days can 30 men complete if they work 5 hours per day?

Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?