Home
Class 14
MATHS
A and B can do a piece of work in 12 day...

A and B can do a piece of work in 12 days and 15 days, respectively. They began to work together but B left after 4 days. In how many more days would B alone complete the remaining work?

A

`(20)/(3)`

B

`(25)/(3)`

C

`(24)/(5)`

D

`(20)/(5)`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will calculate the work done by A and B, and then determine how many more days B would take to complete the remaining work after A and B have worked together for 4 days. ### Step 1: Determine the total work A can complete the work in 12 days, and B can complete it in 15 days. To find the total work, we can take the least common multiple (LCM) of their working days. - LCM of 12 and 15 is 60. ### Step 2: Calculate the efficiency of A and B Efficiency is calculated as the total work divided by the time taken to complete that work. - Efficiency of A = Total Work / Time taken by A = 60 / 12 = 5 - Efficiency of B = Total Work / Time taken by B = 60 / 15 = 4 ### Step 3: Calculate the combined efficiency of A and B When A and B work together, their efficiencies add up. - Combined efficiency of A and B = Efficiency of A + Efficiency of B = 5 + 4 = 9 ### Step 4: Calculate the work done by A and B in 4 days Now that we know their combined efficiency, we can calculate how much work they complete together in 4 days. - Work done in 4 days = Combined efficiency × Number of days = 9 × 4 = 36 ### Step 5: Calculate the remaining work Now we can find out how much work is left after A and B have worked together for 4 days. - Remaining work = Total work - Work done in 4 days = 60 - 36 = 24 ### Step 6: Calculate how long it will take for B to complete the remaining work alone Since B is the one who will complete the remaining work, we need to find out how long it will take B to finish the remaining 24 units of work. - Time taken by B = Remaining work / Efficiency of B = 24 / 4 = 6 days ### Final Answer B will take **6 more days** to complete the remaining work alone. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 1) |40 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise SOLVED EXAMPLE |10 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos