A and B together can do a piece of work ...

A and B together can do a piece of work in 18 days. B and C together can complete the same piece of work in 30 days. If A is 100% more efficient than C. find in how much time B can complete the work alone?

A

22.5 days

B

45 days

C

36 days

D

90 days

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise MAINS QUESTIONS |55 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise BASIC QUESTIONS |15 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -PRELIMS QUESTIONS (LEVEL - 1)
  1. Manoj is 25% less efficient than Hemant. Vikash and Hemant working tog...

    Text Solution

    |

  2. Raghav can do a piece of work in 15 days while Dev can do the same pie...

    Text Solution

    |

  3. A and B together can do a piece of work in 18 days. B and C together c...

    Text Solution

    |

  4. Ravi can do three fourth of a work in (27)/(2) hours while Hira can do...

    Text Solution

    |

  5. Ram and Shyam can do work in 16 days. Shyam takes twice time as Ram ta...

    Text Solution

    |

  6. If 9 men or 15 women can do a piece of work in 18 days working 9 hours...

    Text Solution

    |

  7. Hemant and Vikash working together can make a wall in 15 days. They bo...

    Text Solution

    |

  8. A filling tap can fill a tank in 10 hour. Two equivalent filling tap a...

    Text Solution

    |

  9. Lokesh starts a work and after 6 days he left and remaining work finis...

    Text Solution

    |

  10. Tap D can fill 4 buckets in 36 min and tap E can fill 2 buckets in 12 ...

    Text Solution

    |

  11. 40 men and 20 women together can complete a work in 12 days and ratio ...

    Text Solution

    |

  12. Tap A can fill a tank in 4 hours and with help of tab B it takes 2.4 h...

    Text Solution

    |

  13. A certain job was assigned to a group of men to do it in 24 days. But ...

    Text Solution

    |

  14. A can complete 3//5^(th) of the work in 9 days. A and B together do 1/...

    Text Solution

    |

  15. 15 men can complete a work in 8 days while 10 women can complete the s...

    Text Solution

    |

  16. Rohit can paint a wall in 40 days, while Sohan is 25% more efficient t...

    Text Solution

    |

  17. Two pipes P and Q alone can fill a tank in 24 min and 30 min respectiv...

    Text Solution

    |

  18. Efficiency of Anurag is two times more than efficiency of Ayush. Both ...

    Text Solution

    |

  19. The ratio of efficiency of A to that of B is 5:4. A starts the work al...

    Text Solution

    |

  20. A & B can do a piece of work together in 24 days and C's efficiency is...

    Text Solution

    |