Home
Class 14
MATHS
Lokesh starts a work and after 6 days he...

Lokesh starts a work and after 6 days he left and remaining work finished by Rakesh in 12 days. Had Lokesh worked for 9 days, Rakesh would have finished the remaining work in 8 days. Find the time taken by Lokesh to complete the work alone.

A

12 days

B

9 days

C

15 days

D

18 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will denote Lokesh's efficiency as \( L \) and Rakesh's efficiency as \( R \). ### Step 1: Understand the Work Done Lokesh works for 6 days and then Rakesh completes the remaining work in 12 days. We can express the total work in terms of their efficiencies. ### Step 2: Set Up the Equations From the first condition: - Work done by Lokesh in 6 days = \( 6L \) - Work done by Rakesh in 12 days = \( 12R \) The total work can be expressed as: \[ 6L + 12R = \text{Total Work} \quad (1) \] ### Step 3: Analyze the Second Condition If Lokesh had worked for 9 days, Rakesh would have finished the remaining work in 8 days. - Work done by Lokesh in 9 days = \( 9L \) - Remaining work done by Rakesh in 8 days = \( 8R \) The total work can also be expressed as: \[ 9L + 8R = \text{Total Work} \quad (2) \] ### Step 4: Equate the Total Work from Both Conditions From equations (1) and (2), we can set them equal to each other: \[ 6L + 12R = 9L + 8R \] ### Step 5: Rearranging the Equation Rearranging gives: \[ 12R - 8R = 9L - 6L \] \[ 4R = 3L \] ### Step 6: Find the Ratio of Efficiencies From the equation \( 4R = 3L \), we can express the ratio of Lokesh's efficiency to Rakesh's efficiency: \[ \frac{L}{R} = \frac{4}{3} \] ### Step 7: Express Rakesh's Efficiency in Terms of Lokesh's Let \( R = \frac{3}{4}L \). ### Step 8: Substitute Back to Find Total Work Substituting \( R \) in either equation (1) or (2) to find the total work. Let's use equation (1): \[ 6L + 12\left(\frac{3}{4}L\right) = \text{Total Work} \] \[ 6L + 9L = \text{Total Work} \] \[ 15L = \text{Total Work} \] ### Step 9: Calculate the Time Taken by Lokesh Alone To find the time taken by Lokesh to complete the work alone, we use: \[ \text{Time} = \frac{\text{Total Work}}{\text{Efficiency of Lokesh}} = \frac{15L}{L} = 15 \text{ days} \] ### Final Answer Thus, the time taken by Lokesh to complete the work alone is **15 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise MAINS QUESTIONS |55 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise BASIC QUESTIONS |15 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -PRELIMS QUESTIONS (LEVEL - 1)
  1. Hemant and Vikash working together can make a wall in 15 days. They bo...

    Text Solution

    |

  2. A filling tap can fill a tank in 10 hour. Two equivalent filling tap a...

    Text Solution

    |

  3. Lokesh starts a work and after 6 days he left and remaining work finis...

    Text Solution

    |

  4. Tap D can fill 4 buckets in 36 min and tap E can fill 2 buckets in 12 ...

    Text Solution

    |

  5. 40 men and 20 women together can complete a work in 12 days and ratio ...

    Text Solution

    |

  6. Tap A can fill a tank in 4 hours and with help of tab B it takes 2.4 h...

    Text Solution

    |

  7. A certain job was assigned to a group of men to do it in 24 days. But ...

    Text Solution

    |

  8. A can complete 3//5^(th) of the work in 9 days. A and B together do 1/...

    Text Solution

    |

  9. 15 men can complete a work in 8 days while 10 women can complete the s...

    Text Solution

    |

  10. Rohit can paint a wall in 40 days, while Sohan is 25% more efficient t...

    Text Solution

    |

  11. Two pipes P and Q alone can fill a tank in 24 min and 30 min respectiv...

    Text Solution

    |

  12. Efficiency of Anurag is two times more than efficiency of Ayush. Both ...

    Text Solution

    |

  13. The ratio of efficiency of A to that of B is 5:4. A starts the work al...

    Text Solution

    |

  14. A & B can do a piece of work together in 24 days and C's efficiency is...

    Text Solution

    |

  15. A is 25% more efficient than B. B takes 6 days more time to complete t...

    Text Solution

    |

  16. Efficiency of A is 40% more than that of B and ratio of efficiency of ...

    Text Solution

    |

  17. A and B started the work alternatively starting with A. On last day A ...

    Text Solution

    |

  18. Ayush is thrice as good a workman as Anurag and both working together ...

    Text Solution

    |

  19. A can do a piece of work in 48 days and B can do the same work in 64 d...

    Text Solution

    |

  20. Anurag is 40% less efficient than Bholu, who can do the same work in 2...

    Text Solution

    |