Home
Class 14
MATHS
15 men can complete a work in 8 days whi...

15 men can complete a work in 8 days while 10 women can complete the same work in 20 days. 7 men starts working and after 12 days they are replaced by 10 women. Find time taken by 10 women to complete the remaining work.

A

A)5 days

B

B)8 days

C

C)7 days

D

D)6 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these steps: ### Step 1: Calculate the total work done by men and women. 1. **Men's Work Rate**: - 15 men can complete the work in 8 days. - Therefore, the total work can be calculated as: \[ \text{Total Work} = \text{Number of Men} \times \text{Days} = 15 \times 8 = 120 \text{ man-days} \] 2. **Women's Work Rate**: - 10 women can complete the same work in 20 days. - Therefore, the total work can also be calculated as: \[ \text{Total Work} = \text{Number of Women} \times \text{Days} = 10 \times 20 = 200 \text{ woman-days} \] ### Step 2: Find the work done by 7 men in 12 days. 1. **Efficiency of 1 Man**: - Since 15 men can complete the work in 120 man-days, the work done by 1 man in 1 day is: \[ \text{Work done by 1 man in 1 day} = \frac{1}{120} \text{ of the work} \] 2. **Efficiency of 7 Men**: - Therefore, the work done by 7 men in 1 day is: \[ \text{Work done by 7 men in 1 day} = 7 \times \frac{1}{120} = \frac{7}{120} \] 3. **Work done by 7 Men in 12 Days**: - The total work done by 7 men in 12 days is: \[ \text{Total work done} = 12 \times \frac{7}{120} = \frac{84}{120} = \frac{7}{10} \text{ of the work} \] ### Step 3: Calculate the remaining work. 1. **Remaining Work**: - If 7 men completed \(\frac{7}{10}\) of the work, the remaining work is: \[ \text{Remaining Work} = 1 - \frac{7}{10} = \frac{3}{10} \text{ of the work} \] ### Step 4: Calculate the time taken by 10 women to complete the remaining work. 1. **Efficiency of 10 Women**: - From the previous calculations, we know that 10 women can complete the work in 200 woman-days. - Therefore, the work done by 1 woman in 1 day is: \[ \text{Work done by 1 woman in 1 day} = \frac{1}{200} \] - Thus, the work done by 10 women in 1 day is: \[ \text{Work done by 10 women in 1 day} = 10 \times \frac{1}{200} = \frac{10}{200} = \frac{1}{20} \] 2. **Time Taken by 10 Women to Complete Remaining Work**: - To find the time taken \(T\) by 10 women to complete \(\frac{3}{10}\) of the work: \[ \frac{1}{20} \times T = \frac{3}{10} \] - Solving for \(T\): \[ T = \frac{3}{10} \times 20 = 6 \text{ days} \] ### Final Answer: The time taken by 10 women to complete the remaining work is **6 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise MAINS QUESTIONS |55 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise BASIC QUESTIONS |15 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -PRELIMS QUESTIONS (LEVEL - 1)
  1. A certain job was assigned to a group of men to do it in 24 days. But ...

    Text Solution

    |

  2. A can complete 3//5^(th) of the work in 9 days. A and B together do 1/...

    Text Solution

    |

  3. 15 men can complete a work in 8 days while 10 women can complete the s...

    Text Solution

    |

  4. Rohit can paint a wall in 40 days, while Sohan is 25% more efficient t...

    Text Solution

    |

  5. Two pipes P and Q alone can fill a tank in 24 min and 30 min respectiv...

    Text Solution

    |

  6. Efficiency of Anurag is two times more than efficiency of Ayush. Both ...

    Text Solution

    |

  7. The ratio of efficiency of A to that of B is 5:4. A starts the work al...

    Text Solution

    |

  8. A & B can do a piece of work together in 24 days and C's efficiency is...

    Text Solution

    |

  9. A is 25% more efficient than B. B takes 6 days more time to complete t...

    Text Solution

    |

  10. Efficiency of A is 40% more than that of B and ratio of efficiency of ...

    Text Solution

    |

  11. A and B started the work alternatively starting with A. On last day A ...

    Text Solution

    |

  12. Ayush is thrice as good a workman as Anurag and both working together ...

    Text Solution

    |

  13. A can do a piece of work in 48 days and B can do the same work in 64 d...

    Text Solution

    |

  14. Anurag is 40% less efficient than Bholu, who can do the same work in 2...

    Text Solution

    |

  15. Tap A can fill a tank in 24 minutes and tap B can fill the same tank i...

    Text Solution

    |

  16. Sanjeev can prepare some dishes in 4 hours while Nisha can prepare sam...

    Text Solution

    |

  17. X is 40% more efficient than Y and Z takes 33(1)/(3)% less time than X...

    Text Solution

    |

  18. Anurag can make a video in 10 hours whil Karan can make same video in ...

    Text Solution

    |

  19. A cistern has two pipes. One can fill it with water in 15 hours and ot...

    Text Solution

    |

  20. A and B undertake to do a piece of work for Rs.999. A can do it in 10 ...

    Text Solution

    |