Home
Class 14
MATHS
A can do a piece of work in 48 days and ...

A can do a piece of work in 48 days and B can do the same work in 64 days, while C take as half time as A and B take together. If they start working alternatively, starting by C, followed by B and then A respectively, then find in how many days work will be completed?

A

A)`26(3)/(7)`days

B

B)`28(5)/(7)`days

C

C)`26(1)/(14)`days

D

D)`27(3)/(14)`days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these calculations: ### Step 1: Determine the work rates of A, B, and C - A can complete the work in 48 days. Therefore, A's work rate is: \[ \text{Work rate of A} = \frac{1}{48} \text{ work/day} \] - B can complete the work in 64 days. Therefore, B's work rate is: \[ \text{Work rate of B} = \frac{1}{64} \text{ work/day} \] ### Step 2: Calculate the combined work rate of A and B - The combined work rate of A and B is: \[ \text{Combined work rate of A and B} = \frac{1}{48} + \frac{1}{64} \] - To add these fractions, we need a common denominator. The least common multiple (LCM) of 48 and 64 is 192. \[ \frac{1}{48} = \frac{4}{192}, \quad \frac{1}{64} = \frac{3}{192} \] - Therefore, \[ \text{Combined work rate of A and B} = \frac{4 + 3}{192} = \frac{7}{192} \text{ work/day} \] ### Step 3: Determine C's work rate - C takes half the time of A and B working together. The time taken by A and B together to complete the work is: \[ \text{Time taken by A and B together} = \frac{192}{7} \text{ days} \] - Therefore, C's time to complete the work is: \[ \text{Time taken by C} = \frac{1}{2} \times \frac{192}{7} = \frac{96}{7} \text{ days} \] - C's work rate is: \[ \text{Work rate of C} = \frac{1}{\frac{96}{7}} = \frac{7}{96} \text{ work/day} \] ### Step 4: Calculate the total work done in one complete cycle of C, B, and A - In one cycle (3 days), the work done is: - Day 1 (C): C does \(\frac{7}{96}\) - Day 2 (B): B does \(\frac{1}{64}\) - Day 3 (A): A does \(\frac{1}{48}\) - Total work done in one cycle: \[ \text{Total work in 3 days} = \frac{7}{96} + \frac{1}{64} + \frac{1}{48} \] ### Step 5: Find a common denominator and calculate the total work done in one cycle - The common denominator for 96, 64, and 48 is 192. \[ \frac{7}{96} = \frac{14}{192}, \quad \frac{1}{64} = \frac{3}{192}, \quad \frac{1}{48} = \frac{4}{192} \] - Therefore, \[ \text{Total work in 3 days} = \frac{14 + 3 + 4}{192} = \frac{21}{192} \text{ work} \] ### Step 6: Calculate how many complete cycles are needed to finish the work - The total work is 1 (or 192/192). The number of complete cycles needed: \[ \text{Number of cycles} = \frac{192}{21} \approx 9.14 \text{ cycles} \] - This means 9 complete cycles can be done, which takes: \[ 9 \times 3 = 27 \text{ days} \] ### Step 7: Calculate the remaining work after 9 cycles - Work done in 9 cycles: \[ 9 \times \frac{21}{192} = \frac{189}{192} \] - Remaining work: \[ 1 - \frac{189}{192} = \frac{3}{192} = \frac{1}{64} \] ### Step 8: Determine how long it will take to finish the remaining work - C starts the next cycle and can complete \(\frac{7}{96}\) work in one day. To finish \(\frac{1}{64}\): - Time taken by C to finish \(\frac{1}{64}\): \[ \text{Time} = \frac{\frac{1}{64}}{\frac{7}{96}} = \frac{96}{448} = \frac{3}{14} \text{ days} \] ### Final Calculation - Total time taken to complete the work: \[ 27 + \frac{3}{14} = 27 \frac{3}{14} \text{ days} \] ### Conclusion The total time taken to complete the work is **27 whole 3/14 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise MAINS QUESTIONS |55 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise BASIC QUESTIONS |15 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -PRELIMS QUESTIONS (LEVEL - 1)
  1. The ratio of efficiency of A to that of B is 5:4. A starts the work al...

    Text Solution

    |

  2. A & B can do a piece of work together in 24 days and C's efficiency is...

    Text Solution

    |

  3. A is 25% more efficient than B. B takes 6 days more time to complete t...

    Text Solution

    |

  4. Efficiency of A is 40% more than that of B and ratio of efficiency of ...

    Text Solution

    |

  5. A and B started the work alternatively starting with A. On last day A ...

    Text Solution

    |

  6. Ayush is thrice as good a workman as Anurag and both working together ...

    Text Solution

    |

  7. A can do a piece of work in 48 days and B can do the same work in 64 d...

    Text Solution

    |

  8. Anurag is 40% less efficient than Bholu, who can do the same work in 2...

    Text Solution

    |

  9. Tap A can fill a tank in 24 minutes and tap B can fill the same tank i...

    Text Solution

    |

  10. Sanjeev can prepare some dishes in 4 hours while Nisha can prepare sam...

    Text Solution

    |

  11. X is 40% more efficient than Y and Z takes 33(1)/(3)% less time than X...

    Text Solution

    |

  12. Anurag can make a video in 10 hours whil Karan can make same video in ...

    Text Solution

    |

  13. A cistern has two pipes. One can fill it with water in 15 hours and ot...

    Text Solution

    |

  14. A and B undertake to do a piece of work for Rs.999. A can do it in 10 ...

    Text Solution

    |

  15. A can do a piece of work in 30 days. If A and B together can do (1)/(3...

    Text Solution

    |

  16. A, B and C working alone can finish a work in 80 days, 50 days and 90 ...

    Text Solution

    |

  17. 20 male labours can finish the work in 30 days and 30 female labours c...

    Text Solution

    |

  18. A jewellery merchant gives its employees silver coins as increment. Ja...

    Text Solution

    |

  19. Pipe A can fill (2)/(3)rd of the empty tank in 20 minutes while pipe A...

    Text Solution

    |

  20. Jai & Veeru undertook a work to complete in 5 days for Rs. 800. But wi...

    Text Solution

    |