20 male labours can finish the work in 3...

20 male labours can finish the work in 30 days and 30 female labours can finish the same work in 24 days. If all of them work together, then in how many days they will finish the same work?

A

A)`(28)/(3)`days

B

B)`(20)/(3)`days

C

C)`(40)/(3)`days

D

D)`(34)/(3)`days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these calculations: ### Step 1: Calculate the total work done in terms of units. Given that: - 20 male labours can finish the work in 30 days. To find the total work in units, we can use the formula: \[ \text{Total Work} = \text{Number of Labours} \times \text{Days} \] Thus, for male labours: \[ \text{Total Work} = 20 \text{ labours} \times 30 \text{ days} = 600 \text{ units} \] ### Step 2: Calculate the efficiency of male labours. The efficiency of the male labours can be calculated as: \[ \text{Efficiency of Male Labours} = \frac{\text{Total Work}}{\text{Days}} = \frac{600 \text{ units}}{30 \text{ days}} = 20 \text{ units per day} \] ### Step 3: Calculate the total work done by female labours. Given that: - 30 female labours can finish the work in 24 days. Using the same formula for total work: \[ \text{Total Work} = 30 \text{ labours} \times 24 \text{ days} = 720 \text{ units} \] ### Step 4: Calculate the efficiency of female labours. The efficiency of the female labours can be calculated as: \[ \text{Efficiency of Female Labours} = \frac{\text{Total Work}}{\text{Days}} = \frac{720 \text{ units}}{24 \text{ days}} = 30 \text{ units per day} \] ### Step 5: Calculate the combined efficiency of male and female labours. Now, we can find the combined efficiency when both male and female labours work together: \[ \text{Combined Efficiency} = \text{Efficiency of Male Labours} + \text{Efficiency of Female Labours} \] \[ \text{Combined Efficiency} = 20 \text{ units per day} + 30 \text{ units per day} = 50 \text{ units per day} \] ### Step 6: Calculate the time taken to finish the work together. Now, we can find the time taken to complete the work when both groups work together: \[ \text{Time} = \frac{\text{Total Work}}{\text{Combined Efficiency}} \] Using the total work calculated from either group (let's use the male labours' work): \[ \text{Time} = \frac{600 \text{ units}}{50 \text{ units per day}} = 12 \text{ days} \] ### Final Answer: Thus, if all of them work together, they will finish the work in **12 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise MAINS QUESTIONS |55 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise BASIC QUESTIONS |15 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -PRELIMS QUESTIONS (LEVEL - 1)
  1. The ratio of efficiency of A to that of B is 5:4. A starts the work al...

    Text Solution

    |

  2. A & B can do a piece of work together in 24 days and C's efficiency is...

    Text Solution

    |

  3. A is 25% more efficient than B. B takes 6 days more time to complete t...

    Text Solution

    |

  4. Efficiency of A is 40% more than that of B and ratio of efficiency of ...

    Text Solution

    |

  5. A and B started the work alternatively starting with A. On last day A ...

    Text Solution

    |

  6. Ayush is thrice as good a workman as Anurag and both working together ...

    Text Solution

    |

  7. A can do a piece of work in 48 days and B can do the same work in 64 d...

    Text Solution

    |

  8. Anurag is 40% less efficient than Bholu, who can do the same work in 2...

    Text Solution

    |

  9. Tap A can fill a tank in 24 minutes and tap B can fill the same tank i...

    Text Solution

    |

  10. Sanjeev can prepare some dishes in 4 hours while Nisha can prepare sam...

    Text Solution

    |

  11. X is 40% more efficient than Y and Z takes 33(1)/(3)% less time than X...

    Text Solution

    |

  12. Anurag can make a video in 10 hours whil Karan can make same video in ...

    Text Solution

    |

  13. A cistern has two pipes. One can fill it with water in 15 hours and ot...

    Text Solution

    |

  14. A and B undertake to do a piece of work for Rs.999. A can do it in 10 ...

    Text Solution

    |

  15. A can do a piece of work in 30 days. If A and B together can do (1)/(3...

    Text Solution

    |

  16. A, B and C working alone can finish a work in 80 days, 50 days and 90 ...

    Text Solution

    |

  17. 20 male labours can finish the work in 30 days and 30 female labours c...

    Text Solution

    |

  18. A jewellery merchant gives its employees silver coins as increment. Ja...

    Text Solution

    |

  19. Pipe A can fill (2)/(3)rd of the empty tank in 20 minutes while pipe A...

    Text Solution

    |

  20. Jai & Veeru undertook a work to complete in 5 days for Rs. 800. But wi...

    Text Solution

    |