C is 100% more efficient than B. A alone...

C is 100% more efficient than B. A alone can complete a piece of work in 9 days and B & C together can complete the same work in `2(2)/(3)` days. Find what portion of work will be completed, if A & B works together for 4 days.

A

`(13)/(18)`

B

`(8)/(9)`

C

`(5)/(6)`

D

`(17)/(18)`

Text Solution

Verified by Experts

Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise MAINS QUESTIONS |55 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -PREVIOUS YEAR QUESTIONS
  1. C is 100% more efficient than B. A alone can complete a piece of work ...

    Text Solution

    |

  2. A alone can fill a tank in 16 mins and B alone can fill the same tank ...

    Text Solution

    |

  3. If Pipes A and B can fill a tank in 15 min and 20 mins respectively an...

    Text Solution

    |

  4. A, B and C together can complete a work in 8 days and A alone can comp...

    Text Solution

    |

  5. Two inlet taps A and B can fill a tank in 36 minutes and 60 minutes re...

    Text Solution

    |

  6. Efficiency of A is 40% more than that of B and ratio of efficiency of ...

    Text Solution

    |

  7. 8 men and 10 women can do a work in 15 days while 10 men and 18 women ...

    Text Solution

    |

  8. A, B & C are three inlet pipes. Time taken by A & B together to fill h...

    Text Solution

    |

  9. What approximate value will come in place of the question mark (?) in ...

    Text Solution

    |

  10. 12 men can do a work in 10 days while 10 women can do the same work in...

    Text Solution

    |

  11. The ratio of time taken by A, B & C to complete work alone is 4 : 6 : ...

    Text Solution

    |

  12. A & B together can complete a piece of work in 9 days. Time taken by A...

    Text Solution

    |

  13. 12 women can complete a work in 64 day, then find how many women will ...

    Text Solution

    |

  14. Shivam alone and Deepak alone can finish a task in 6 hours and 10 hour...

    Text Solution

    |

  15. 40 men can complete a work in 48 days 64 men started for the same work...

    Text Solution

    |

  16. A alone can do a work in 12 days while A and B together can do that wo...

    Text Solution

    |

  17. A can complete a piece of work in 33 days and C is three times more ef...

    Text Solution

    |

  18. A is twice as good a workman as B and together they finish a piece of ...

    Text Solution

    |

  19. Kamal can do a work in 15 days. Bimal is 50 per cent more efficient th...

    Text Solution

    |

  20. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |