A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

A

10 days

B

12 days

C

15 days

D

16 days

Text Solution

Verified by Experts

The correct Answer is:
C