Home
Class 14
MATHS
An engineer undertakes a project to buil...

An engineer undertakes a project to build a road15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) numbe of extra men he must employ to finish the work in time.

A

43

B

45

C

55

D

68

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we need to determine how many extra men are required to complete the road project on time. Here’s how we can do it: ### Step 1: Determine the total work required The total length of the road to be built is 15 km. ### Step 2: Calculate the work completed in 100 days After 100 days, the engineer has completed 2.5 km of the road. ### Step 3: Calculate the remaining work Remaining work = Total work - Work completed Remaining work = 15 km - 2.5 km = 12.5 km ### Step 4: Calculate the remaining time Total time for the project = 300 days Time already spent = 100 days Remaining time = 300 days - 100 days = 200 days ### Step 5: Determine the work rate of the current workforce The current workforce is 45 men. We need to find out how much work these men can do in the remaining time. ### Step 6: Use the formula for work The formula for work is: \[ M_1 \times D_1 \times W_2 = M_2 \times D_2 \times W_1 \] Where: - \( M_1 \) = initial number of men = 45 - \( D_1 \) = initial time spent = 100 days - \( W_2 \) = remaining work = 12.5 km - \( M_2 \) = required number of men (unknown) - \( D_2 \) = remaining time = 200 days - \( W_1 \) = work completed = 2.5 km ### Step 7: Rearranging the formula We can rearrange the formula to find \( M_2 \): \[ M_2 = \frac{M_1 \times D_1 \times W_2}{D_2 \times W_1} \] ### Step 8: Substitute the values into the equation Substituting the known values: \[ M_2 = \frac{45 \times 100 \times 12.5}{200 \times 2.5} \] ### Step 9: Calculate the right side of the equation Calculating the numerator: \[ 45 \times 100 \times 12.5 = 56250 \] Calculating the denominator: \[ 200 \times 2.5 = 500 \] Now, substituting these values: \[ M_2 = \frac{56250}{500} = 112.5 \] ### Step 10: Round up the number of men Since we cannot have a fraction of a man, we round up to the nearest whole number, which is 113 men. ### Step 11: Calculate the extra men required Extra men required = \( M_2 - M_1 \) Extra men required = \( 113 - 45 = 68 \) ### Final Answer The engineer must employ approximately **68 extra men** to finish the work on time. ---
Promotional Banner