Home
Class 14
MATHS
Aditya, Vedus and Yuvraj alone can do a ...

Aditya, Vedus and Yuvraj alone can do a job for 6 weeks, 9 weeks and 12 weeks respectively. They work together for 2 weeks. Then, Aditya leaves the job. Vedus leaves the job a week earlier to the completion of the work. The job would be completed in:

A

4 weeks

B

5 weeks

C

7 weeks

D

None of these

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step-by-step, let's break it down: ### Step 1: Determine the work done by each person in one week. - **Aditya's work rate:** He can complete the job in 6 weeks, so his work rate is \( \frac{1}{6} \) of the job per week. - **Vedus's work rate:** He can complete the job in 9 weeks, so his work rate is \( \frac{1}{9} \) of the job per week. - **Yuvraj's work rate:** He can complete the job in 12 weeks, so his work rate is \( \frac{1}{12} \) of the job per week. ### Step 2: Calculate the combined work rate when all three work together. - Combined work rate = \( \frac{1}{6} + \frac{1}{9} + \frac{1}{12} \) To add these fractions, we need a common denominator. The least common multiple (LCM) of 6, 9, and 12 is 36. - Convert each fraction: - \( \frac{1}{6} = \frac{6}{36} \) - \( \frac{1}{9} = \frac{4}{36} \) - \( \frac{1}{12} = \frac{3}{36} \) Now, add them together: \[ \frac{6}{36} + \frac{4}{36} + \frac{3}{36} = \frac{13}{36} \] ### Step 3: Calculate the total work done in 2 weeks. - Work done in 2 weeks = \( 2 \times \frac{13}{36} = \frac{26}{36} = \frac{13}{18} \) of the job. ### Step 4: Determine the remaining work. - Total work = 1 (the whole job). - Remaining work = \( 1 - \frac{13}{18} = \frac{5}{18} \) of the job. ### Step 5: Determine who works next and their work rates. - After 2 weeks, Aditya leaves. Now, Vedus and Yuvraj will work together. - Combined work rate of Vedus and Yuvraj = \( \frac{1}{9} + \frac{1}{12} \) Convert these fractions to a common denominator: - LCM of 9 and 12 is 36. - Convert: - \( \frac{1}{9} = \frac{4}{36} \) - \( \frac{1}{12} = \frac{3}{36} \) Combined work rate = \( \frac{4}{36} + \frac{3}{36} = \frac{7}{36} \) ### Step 6: Calculate the work done by Vedus and Yuvraj in 1 week. - Work done in 1 week = \( \frac{7}{36} \). ### Step 7: Determine the remaining work after Vedus leaves. - Vedus leaves a week earlier, so they work together for 1 week. - Work done in 1 week = \( \frac{7}{36} \). - Remaining work = \( \frac{5}{18} - \frac{7}{36} \). Convert \( \frac{5}{18} \) to a fraction with a denominator of 36: - \( \frac{5}{18} = \frac{10}{36} \). Now, calculate remaining work: \[ \frac{10}{36} - \frac{7}{36} = \frac{3}{36} = \frac{1}{12} \] ### Step 8: Determine how long Yuvraj will take to finish the remaining work. - Yuvraj's work rate is \( \frac{1}{12} \). - Time taken to finish \( \frac{1}{12} \) of the job = \( \frac{1/12}{1/12} = 1 \) week. ### Step 9: Calculate the total time taken to complete the job. - Total time = 2 weeks (initial work) + 1 week (Vedus and Yuvraj) + 1 week (Yuvraj alone) = 4 weeks. ### Final Answer: The job would be completed in **4 weeks**. ---
Promotional Banner