A .can finish a piece of work in 24 days...

A .can finish a piece of work in 24 days B is `20%` more efficient than A. C is `25%` more efficient than B. In how many days B and C together can finish the same piece of work?

A

`8 8/9`

B

`9 1/3`

C

`8 5/8`

D

`10 2/9`

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

A can do a piece ofwork in 14 days and B is 40% more efficient than A.In how many days can B finish it?

A can do a work in 15 days. B is 25% more effcient than a In how many days working together A and B is complete the same work ?

A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?

X can do a piece of work in 25 days. Y is 25% more efficient than X. The number of days taken by Y is :

A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?