Neelam, Usha, Meena can do a work in 10,...

Neelam, Usha, Meena can do a work in 10, 12 and 15 days respectively. If Usha left after 2 days. How long would it take Neelam and Meena to complete the remaining work ?

Text Solution

Verified by Experts

The part of work completed by Neelam, Usha and Meena in 2 days `because`Remaining work = `1 – 1 /2 = 1 /2`
`therefore` Work done by (Neelam and Meena) together in 1 day `because 1/6 th` part of work completed by both Neelam and Meena in 1 day
`because 1/2` part of work will be completed in = `1/(1/6)xx1/ 2`
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

Ram and Mohan can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days Mohan had to leave and Ram alone completed the remaining work The whole work was completed in:

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

A,B and C can do a piece of work in 15,12 and 20 days respectively.They started the work together,but C left after 2 days.In how many days will the remaining work be completed by A and B?

A and B can do a job in 12 days, B and C in 15 days and C and A in 20 days. How long would A take to do that work?

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. Dinesh and Ram can do a working 80 minutes and 120 minutes respectivel...

    Text Solution

    |

  2. Neelam, Usha, Meena can do a work in 10, 12 and 15 days respectively. ...

    Text Solution

    |

  3. A can do 3/4th part of a work in 10 days and B completed the remaining...

    Text Solution

    |

  4. A can do a work in 12 days. B works 60% more fast than A then in how m...

    Text Solution

    |

  5. If 5 men and 2 boys working together can do four times as much work pe...

    Text Solution

    |

  6. One man, 2 women and 3 boys working together do a work in 36 days, whi...

    Text Solution

    |

  7. Uday working 4 hours a day completes a work in 10 days, while Subhash ...

    Text Solution

    |

  8. A is two times work eficient than B and three times than C. If C alone...

    Text Solution

    |

  9. Twenty four men can complete a work in sixteen days. Thirty two women ...

    Text Solution

    |

  10. A can do a piece of work in 30 days while B can do it in 40 days. In h...

    Text Solution

    |

  11. 25 men and 15 women can complete a piece of work in 12 days. All of th...

    Text Solution

    |

  12. A and B together do a piece of work in 15 days. B can do it alone in 2...

    Text Solution

    |

  13. 10 men and 15 women finish a work in 6 days. One man alone finishes th...

    Text Solution

    |

  14. A and B can do a piece of work in 6 days and A alone can do it in 9 da...

    Text Solution

    |

  15. A can do a piece of work in 12 days. B can do the same work in 8 days ...

    Text Solution

    |

  16. A can do (1/3) of a work in 5 days and B can do (2/5) of the work in 1...

    Text Solution

    |

  17. A completes a work in 15 days. B completes the same work in 20 days. A...

    Text Solution

    |

  18. A and B can do a piece of work in 18 days .B and C in 24 days and A an...

    Text Solution

    |

  19. A can do a piece of work in 10 days and B can dothe same piece of work...

    Text Solution

    |

  20. Twelve men can complete a work in 8 days. Three days after they starte...

    Text Solution

    |