A can do a piece of work in 30 days whil...

A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

A

70 days

B

`42(3)/4` days

C

`27(1)/7`days

D

`17(1)/7` days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem of how many days A and B can complete a piece of work together, we can follow these steps: ### Step 1: Determine the Work Done by A and B Individually - A can complete the work in 30 days. - B can complete the work in 40 days. ### Step 2: Calculate the Efficiency of A and B - Efficiency is calculated as the amount of work done in one day. - For A: \[ \text{Efficiency of A} = \frac{1 \text{ work}}{30 \text{ days}} = \frac{1}{30} \] - For B: \[ \text{Efficiency of B} = \frac{1 \text{ work}}{40 \text{ days}} = \frac{1}{40} \] ### Step 3: Calculate the Combined Efficiency of A and B - To find the combined efficiency, we add the efficiencies of A and B: \[ \text{Combined Efficiency} = \text{Efficiency of A} + \text{Efficiency of B} = \frac{1}{30} + \frac{1}{40} \] - To add these fractions, we need a common denominator. The least common multiple of 30 and 40 is 120. \[ \frac{1}{30} = \frac{4}{120} \quad \text{and} \quad \frac{1}{40} = \frac{3}{120} \] - Now, adding the fractions: \[ \text{Combined Efficiency} = \frac{4}{120} + \frac{3}{120} = \frac{7}{120} \] ### Step 4: Calculate the Time Taken to Complete the Work Together - The time taken to complete the work together can be calculated using the formula: \[ \text{Time} = \frac{\text{Total Work}}{\text{Combined Efficiency}} \] - Assuming the total work is 1 unit, we have: \[ \text{Time} = \frac{1}{\frac{7}{120}} = \frac{120}{7} \approx 17.14 \text{ days} \] ### Conclusion - A and B together can complete the work in approximately \( \frac{120}{7} \) days, which is about 17.14 days.
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?

A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?

A alone can do a piece of work in 10 days and B alone can do it in 15 days. In how many days will A and B together do the same work?

A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. In how many days can A alone finish the work?

Rajan can do a piece of work in 24 days while Amit can do it in 30 days. In how many days can they complete it they work together?

A and B together can do a piece of work in 12 days and A alone can do it in 18 days. In how many days canBalone do it?

A can do a work in 20 days and B can do the same work in 30 days. In how many days, can A and B together do the work? (A) 10 (B) 12 (C) 15 (D) 16

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. A is two times work eficient than B and three times than C. If C alone...

    Text Solution

    |

  2. Twenty four men can complete a work in sixteen days. Thirty two women ...

    Text Solution

    |

  3. A can do a piece of work in 30 days while B can do it in 40 days. In h...

    Text Solution

    |

  4. 25 men and 15 women can complete a piece of work in 12 days. All of th...

    Text Solution

    |

  5. A and B together do a piece of work in 15 days. B can do it alone in 2...

    Text Solution

    |

  6. 10 men and 15 women finish a work in 6 days. One man alone finishes th...

    Text Solution

    |

  7. A and B can do a piece of work in 6 days and A alone can do it in 9 da...

    Text Solution

    |

  8. A can do a piece of work in 12 days. B can do the same work in 8 days ...

    Text Solution

    |

  9. A can do (1/3) of a work in 5 days and B can do (2/5) of the work in 1...

    Text Solution

    |

  10. A completes a work in 15 days. B completes the same work in 20 days. A...

    Text Solution

    |

  11. A and B can do a piece of work in 18 days .B and C in 24 days and A an...

    Text Solution

    |

  12. A can do a piece of work in 10 days and B can dothe same piece of work...

    Text Solution

    |

  13. Twelve men can complete a work in 8 days. Three days after they starte...

    Text Solution

    |

  14. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  15. A can complete a work in 9 days, B in 10 days and C in 15 days. B and ...

    Text Solution

    |

  16. A, B and C contract a work for ₹ 550 together. A and B are supposed to...

    Text Solution

    |

  17. Sunil completes a work in 4 days, whereas Dinesh completes the work in...

    Text Solution

    |

  18. A can do a piece of work in 20 days which B can do in 12 days. B worke...

    Text Solution

    |

  19. Mahesh and Umesh can complete a work in 10 days and 15 days respective...

    Text Solution

    |

  20. A can do a piece of work in 80 days. He works at it for 10 days and th...

    Text Solution

    |