Home
Class 14
MATHS
A piece of work was to be completed in 4...

A piece of work was to be completed in 40 days a number of men employed upon it did only half the work in 24 days, 16 more men were then set on, and the work was completed in the specified time, how many men were employed at first ?

A

16 men

B

32 men

C

24 men

D

48 men

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Understand the Work Done The total work is to be completed in 40 days. According to the problem, half of the work was completed in 24 days. **Hint:** Identify the total work in terms of days and the fraction of work done. ### Step 2: Calculate the Total Work Let the total work be represented as W. Since half of the work is done in 24 days, we can say: \[ \text{Work done in 24 days} = \frac{W}{2} \] ### Step 3: Determine the Work Rate Let the number of men employed initially be \( n \). The work done by \( n \) men in 24 days can be expressed as: \[ n \times 24 = \frac{W}{2} \] From this, we can derive the work done by one man in one day: \[ n = \frac{W}{48} \] ### Step 4: Calculate Remaining Work Since half of the work is completed, the remaining work is also \( \frac{W}{2} \). This remaining work needs to be completed in the remaining days, which is: \[ 40 - 24 = 16 \text{ days} \] ### Step 5: Set Up the Equation for Remaining Work After 24 days, 16 more men are added, making the total number of men: \[ n + 16 \] The equation for the remaining work can be set up as: \[ (n + 16) \times 16 = \frac{W}{2} \] ### Step 6: Substitute \( n \) into the Equation Now we substitute \( n \) from Step 3 into the equation: \[ \left(\frac{W}{48} + 16\right) \times 16 = \frac{W}{2} \] ### Step 7: Simplify the Equation Expanding the left side: \[ \frac{W \times 16}{48} + 16 \times 16 = \frac{W}{2} \] This simplifies to: \[ \frac{W}{3} + 256 = \frac{W}{2} \] ### Step 8: Solve for W To solve for W, we can first eliminate the fractions by multiplying through by 6 (the least common multiple of 3 and 2): \[ 2W + 1536 = 3W \] Rearranging gives: \[ 3W - 2W = 1536 \] Thus: \[ W = 1536 \] ### Step 9: Find the Initial Number of Men Now that we have W, we can find \( n \): \[ n = \frac{W}{48} = \frac{1536}{48} = 32 \] ### Conclusion The number of men employed at first was **32**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?

24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?

15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. If 5 men and 3 boys can reap 23 hectares in 4 days and if 3 men and 2 ...

    Text Solution

    |

  2. 12 men can complete a work within 9 days. After 3 days they started th...

    Text Solution

    |

  3. A piece of work was to be completed in 40 days a number of men employe...

    Text Solution

    |

  4. 25 men reap a field in 20 days. When should 15 men leave the work, if ...

    Text Solution

    |

  5. A can do a certain job in 12 days. B in 60% more efficient than A. Wha...

    Text Solution

    |

  6. 15 men would finish a piece of work in 210 days. But at the end of eve...

    Text Solution

    |

  7. Ramesh can finish a job in 20 days. He worked for 10 days alone and co...

    Text Solution

    |

  8. A can copy 75 pages in 25 hours. A and B together can copy 135 pages i...

    Text Solution

    |

  9. A can do a piece of work in 5 hours, B in 9 hours and C in 15 hours. I...

    Text Solution

    |

  10. Mohan can move his lawn in x hours after 2 hour it begins to rain. The...

    Text Solution

    |

  11. A can do a piece of work in 24 days while B alone can do it in 16 days...

    Text Solution

    |

  12. The rates of working of A and B are in the ratio 3:4.The number of day...

    Text Solution

    |

  13. A and B can together finish a work in 30 days. They worked for it for ...

    Text Solution

    |

  14. A can do a certain job in 12 days. B in 60% more efficient than A. Wha...

    Text Solution

    |

  15. A, B and C together earn Rs. 150 per day while A and C together earn R...

    Text Solution

    |

  16. A alone can finish a work in 10 days and B alone can do it in 15 days....

    Text Solution

    |

  17. A alone can do a piece of work in 6 days and B alone can do it in 8 da...

    Text Solution

    |

  18. A can do a piece of work in 14 days which B can do in 21 days. They...

    Text Solution

    |

  19. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  20. A and B working separately can do a piece of work in 9 and 12 days ...

    Text Solution

    |