A can do a certain job in 12 days. B in 60% more efficient than A. What is the number of days it takes B to do the same piece of work ?

A

`7 1/2`

B

`6 1/4`

C

8

D

6

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

P can do a piece of work in 9 days.Q is 50% more efficient than P. The number of days it takes for Q to do the same piece of work is :

A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?

A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is :

A can do a certain job in 12 days.B is 60% more efficient than A.how many days does B alone take to do the same job?

Kamal can do a work n15 days.Bimal is 50% more efficient than Kamal.The number of days,Bimal will take to do the same piece of work is 7(1)/(2) b.10 c.14 d.12

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. A piece of work was to be completed in 40 days a number of men employe...

    Text Solution

    |

  2. 25 men reap a field in 20 days. When should 15 men leave the work, if ...

    Text Solution

    |

  3. A can do a certain job in 12 days. B in 60% more efficient than A. Wha...

    Text Solution

    |

  4. 15 men would finish a piece of work in 210 days. But at the end of eve...

    Text Solution

    |

  5. Ramesh can finish a job in 20 days. He worked for 10 days alone and co...

    Text Solution

    |

  6. A can copy 75 pages in 25 hours. A and B together can copy 135 pages i...

    Text Solution

    |

  7. A can do a piece of work in 5 hours, B in 9 hours and C in 15 hours. I...

    Text Solution

    |

  8. Mohan can move his lawn in x hours after 2 hour it begins to rain. The...

    Text Solution

    |

  9. A can do a piece of work in 24 days while B alone can do it in 16 days...

    Text Solution

    |

  10. The rates of working of A and B are in the ratio 3:4.The number of day...

    Text Solution

    |

  11. A and B can together finish a work in 30 days. They worked for it for ...

    Text Solution

    |

  12. A can do a certain job in 12 days. B in 60% more efficient than A. Wha...

    Text Solution

    |

  13. A, B and C together earn Rs. 150 per day while A and C together earn R...

    Text Solution

    |

  14. A alone can finish a work in 10 days and B alone can do it in 15 days....

    Text Solution

    |

  15. A alone can do a piece of work in 6 days and B alone can do it in 8 da...

    Text Solution

    |

  16. A can do a piece of work in 14 days which B can do in 21 days. They...

    Text Solution

    |

  17. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  18. A and B working separately can do a piece of work in 9 and 12 days ...

    Text Solution

    |

  19. If factory A turns out x cars an hour and factory B turns out y cars e...

    Text Solution

    |

  20. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |