The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio

A

`3 : 4`

B

`9 : 16`

C

`4 : 3`

D

None of these

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

The rates of working of two tapes A and B are in the ratio 2:3. The ratio of the time taken by A and B respectively to fill a given cistern is

A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :

If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. Mohan can move his lawn in x hours after 2 hour it begins to rain. The...

    Text Solution

    |

  2. A can do a piece of work in 24 days while B alone can do it in 16 days...

    Text Solution

    |

  3. The rates of working of A and B are in the ratio 3:4.The number of day...

    Text Solution

    |

  4. A and B can together finish a work in 30 days. They worked for it for ...

    Text Solution

    |

  5. A can do a certain job in 12 days. B in 60% more efficient than A. Wha...

    Text Solution

    |

  6. A, B and C together earn Rs. 150 per day while A and C together earn R...

    Text Solution

    |

  7. A alone can finish a work in 10 days and B alone can do it in 15 days....

    Text Solution

    |

  8. A alone can do a piece of work in 6 days and B alone can do it in 8 da...

    Text Solution

    |

  9. A can do a piece of work in 14 days which B can do in 21 days. They...

    Text Solution

    |

  10. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  11. A and B working separately can do a piece of work in 9 and 12 days ...

    Text Solution

    |

  12. If factory A turns out x cars an hour and factory B turns out y cars e...

    Text Solution

    |

  13. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  14. Two workers A and B working together completed a job in 5 days. If A...

    Text Solution

    |

  15. A is twice as good a workman as B and together they finish a piece of ...

    Text Solution

    |

  16. A is thrice as good a workman as B and takes 10 days less to do a piec...

    Text Solution

    |

  17. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  18. If 3 men or 4 women can construct a wall in 43 days. Then the number o...

    Text Solution

    |

  19. 12 men or 18 women can reap a field in 14 days. The number of days tha...

    Text Solution

    |

  20. A and B can do a piece of work in 45 and 40 days respectively. They be...

    Text Solution

    |