A can do a certain job in 12 days. B in 60% more efficient than A. What is the number of days it takes B to do the same piece of work ?

A

6

B

`6 1/4`

C

`6 2/3`

D

8

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

P can do a piece of work in 9 days.Q is 50% more efficient than P. The number of days it takes for Q to do the same piece of work is :

A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?

A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is :

A can do a certain job in 12 days.B is 60% more efficient than A.how many days does B alone take to do the same job?

Kamal can do a work n15 days.Bimal is 50% more efficient than Kamal.The number of days,Bimal will take to do the same piece of work is 7(1)/(2) b.10 c.14 d.12

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. The rates of working of A and B are in the ratio 3:4.The number of day...

    Text Solution

    |

  2. A and B can together finish a work in 30 days. They worked for it for ...

    Text Solution

    |

  3. A can do a certain job in 12 days. B in 60% more efficient than A. Wha...

    Text Solution

    |

  4. A, B and C together earn Rs. 150 per day while A and C together earn R...

    Text Solution

    |

  5. A alone can finish a work in 10 days and B alone can do it in 15 days....

    Text Solution

    |

  6. A alone can do a piece of work in 6 days and B alone can do it in 8 da...

    Text Solution

    |

  7. A can do a piece of work in 14 days which B can do in 21 days. They...

    Text Solution

    |

  8. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  9. A and B working separately can do a piece of work in 9 and 12 days ...

    Text Solution

    |

  10. If factory A turns out x cars an hour and factory B turns out y cars e...

    Text Solution

    |

  11. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  12. Two workers A and B working together completed a job in 5 days. If A...

    Text Solution

    |

  13. A is twice as good a workman as B and together they finish a piece of ...

    Text Solution

    |

  14. A is thrice as good a workman as B and takes 10 days less to do a piec...

    Text Solution

    |

  15. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  16. If 3 men or 4 women can construct a wall in 43 days. Then the number o...

    Text Solution

    |

  17. 12 men or 18 women can reap a field in 14 days. The number of days tha...

    Text Solution

    |

  18. A and B can do a piece of work in 45 and 40 days respectively. They be...

    Text Solution

    |

  19. 10 men can finish a piece of work in 10 days, whereas 12 women can fin...

    Text Solution

    |

  20. A certain number of men com plete a piece of work in 60 days. If there...

    Text Solution

    |