A can do a piece of work in 14 days whic...

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is `6 3/5` b. `8 1/2` c. `10 1/5` d. `13 1/2`

A

`6 3/5`days

B

`8 1/2`days

C

`10 1/5`days

D

`13 1/2`days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .

A can do a piece of work in 10 days and B in 20 days.They begin together but A leaves 2 days before the completion of the work.The whole work will be done in?

Raja can do a piece of work in 14 days, while Rani can do the same work in 21 days. They started the work together but 3 days before the completion of the work, Raja left the work. The total number of days to complete the work is :

A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?

A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?

A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. A alone can finish a work in 10 days and B alone can do it in 15 days....

    Text Solution

    |

  2. A alone can do a piece of work in 6 days and B alone can do it in 8 da...

    Text Solution

    |

  3. A can do a piece of work in 14 days which B can do in 21 days. They...

    Text Solution

    |

  4. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  5. A and B working separately can do a piece of work in 9 and 12 days ...

    Text Solution

    |

  6. If factory A turns out x cars an hour and factory B turns out y cars e...

    Text Solution

    |

  7. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  8. Two workers A and B working together completed a job in 5 days. If A...

    Text Solution

    |

  9. A is twice as good a workman as B and together they finish a piece of ...

    Text Solution

    |

  10. A is thrice as good a workman as B and takes 10 days less to do a piec...

    Text Solution

    |

  11. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  12. If 3 men or 4 women can construct a wall in 43 days. Then the number o...

    Text Solution

    |

  13. 12 men or 18 women can reap a field in 14 days. The number of days tha...

    Text Solution

    |

  14. A and B can do a piece of work in 45 and 40 days respectively. They be...

    Text Solution

    |

  15. 10 men can finish a piece of work in 10 days, whereas 12 women can fin...

    Text Solution

    |

  16. A certain number of men com plete a piece of work in 60 days. If there...

    Text Solution

    |

  17. If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 wom...

    Text Solution

    |

  18. 4 men and 6 women finish a job in 8 days, while 3 men and 7 women fini...

    Text Solution

    |

  19. 8 children and 12 men complete a certain piece of work in 9 days. Each...

    Text Solution

    |

  20. 3 men and 4 boys do a piece of work in 8 days, while 4 men and 4 boys ...

    Text Solution

    |