A and B can do a piece of work in 45 and...

A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave

A

6 days

B

8 days

C

9 days

D

12 days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?

A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

A and B can do a piece of work in 28 and 35 days respectively.They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave? 7(5)/(9) days b. 8) days c.9backslash days d.14(2)/(5) days

A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?

A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. If 3 men or 4 women can construct a wall in 43 days. Then the number o...

    Text Solution

    |

  2. 12 men or 18 women can reap a field in 14 days. The number of days tha...

    Text Solution

    |

  3. A and B can do a piece of work in 45 and 40 days respectively. They be...

    Text Solution

    |

  4. 10 men can finish a piece of work in 10 days, whereas 12 women can fin...

    Text Solution

    |

  5. A certain number of men com plete a piece of work in 60 days. If there...

    Text Solution

    |

  6. If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 wom...

    Text Solution

    |

  7. 4 men and 6 women finish a job in 8 days, while 3 men and 7 women fini...

    Text Solution

    |

  8. 8 children and 12 men complete a certain piece of work in 9 days. Each...

    Text Solution

    |

  9. 3 men and 4 boys do a piece of work in 8 days, while 4 men and 4 boys ...

    Text Solution

    |

  10. 8 men can dig a pit in 20 days. If a man works half as much again as a...

    Text Solution

    |

  11. If 1 man or 2 women or 3 boys can do a piece of work in 44 days, then ...

    Text Solution

    |

  12. 2 men and 3 women can finish a piece of work in 10 days, while 4 men c...

    Text Solution

    |

  13. Two men undertake to do a piece of work for Rs. 400. One alone can do ...

    Text Solution

    |

  14. 16 men and 12 women together complete a work in 20 days. If 18 women c...

    Text Solution

    |

  15. A report of 100 pages is to be typed by three typists. Typist A can ty...

    Text Solution

    |

  16. 14 workers can make 1400 toys in 5 days. One day after they started th...

    Text Solution

    |

  17. 24 boys can complete a work in 12 days while 16 men can complete the s...

    Text Solution

    |

  18. 15 men can complete a work in 10 days while 20 boys can complete the s...

    Text Solution

    |

  19. 14 men can complete a work in 12 days. 4 days after they started the w...

    Text Solution

    |

  20. 14 persons can complete a work in 16 days. 8 persons started the work ...

    Text Solution

    |