10 men can finish a piece of work in 10 ...

10 men can finish a piece of work in 10 days, whereas 12 women can finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days they will take to complete it ?

A

2

B

4

C

5

D

11

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

20 men can finish a certain work in 10 days, where as it takes 12 women to finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days will they take to complete it?

If 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. 12 men or 18 women can reap a field in 14 days. The number of days tha...

    Text Solution

    |

  2. A and B can do a piece of work in 45 and 40 days respectively. They be...

    Text Solution

    |

  3. 10 men can finish a piece of work in 10 days, whereas 12 women can fin...

    Text Solution

    |

  4. A certain number of men com plete a piece of work in 60 days. If there...

    Text Solution

    |

  5. If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 wom...

    Text Solution

    |

  6. 4 men and 6 women finish a job in 8 days, while 3 men and 7 women fini...

    Text Solution

    |

  7. 8 children and 12 men complete a certain piece of work in 9 days. Each...

    Text Solution

    |

  8. 3 men and 4 boys do a piece of work in 8 days, while 4 men and 4 boys ...

    Text Solution

    |

  9. 8 men can dig a pit in 20 days. If a man works half as much again as a...

    Text Solution

    |

  10. If 1 man or 2 women or 3 boys can do a piece of work in 44 days, then ...

    Text Solution

    |

  11. 2 men and 3 women can finish a piece of work in 10 days, while 4 men c...

    Text Solution

    |

  12. Two men undertake to do a piece of work for Rs. 400. One alone can do ...

    Text Solution

    |

  13. 16 men and 12 women together complete a work in 20 days. If 18 women c...

    Text Solution

    |

  14. A report of 100 pages is to be typed by three typists. Typist A can ty...

    Text Solution

    |

  15. 14 workers can make 1400 toys in 5 days. One day after they started th...

    Text Solution

    |

  16. 24 boys can complete a work in 12 days while 16 men can complete the s...

    Text Solution

    |

  17. 15 men can complete a work in 10 days while 20 boys can complete the s...

    Text Solution

    |

  18. 14 men can complete a work in 12 days. 4 days after they started the w...

    Text Solution

    |

  19. 14 persons can complete a work in 16 days. 8 persons started the work ...

    Text Solution

    |

  20. Rohan and Sunil separately can complete a work in 8 hours and 4 hours ...

    Text Solution

    |