15 men can complete a work in 10 days wh...

15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days How many days will 10 men and 10 boys together take to complete the same work ?

A

10 days

B

8 days

C

12 days

D

9 days

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

12 men or 30 boys can complete a work in 72 days. How many days will 48 men and 24 boys will take to complete the same work?

Three men can complete a piece of work in 18 days. 6 boys can also complete the same piece of work in 18 days. In how many days will 4 men and 4 boys together complete the same piece of work?

12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

12 men or 24 boys can do a work in 20 days. In how many days, will 24 men and 12 boys together complete the same work ?

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. 3 men and 4 boys do a piece of work in 8 days, while 4 men and 4 boys ...

    Text Solution

    |

  2. 8 men can dig a pit in 20 days. If a man works half as much again as a...

    Text Solution

    |

  3. If 1 man or 2 women or 3 boys can do a piece of work in 44 days, then ...

    Text Solution

    |

  4. 2 men and 3 women can finish a piece of work in 10 days, while 4 men c...

    Text Solution

    |

  5. Two men undertake to do a piece of work for Rs. 400. One alone can do ...

    Text Solution

    |

  6. 16 men and 12 women together complete a work in 20 days. If 18 women c...

    Text Solution

    |

  7. A report of 100 pages is to be typed by three typists. Typist A can ty...

    Text Solution

    |

  8. 14 workers can make 1400 toys in 5 days. One day after they started th...

    Text Solution

    |

  9. 24 boys can complete a work in 12 days while 16 men can complete the s...

    Text Solution

    |

  10. 15 men can complete a work in 10 days while 20 boys can complete the s...

    Text Solution

    |

  11. 14 men can complete a work in 12 days. 4 days after they started the w...

    Text Solution

    |

  12. 14 persons can complete a work in 16 days. 8 persons started the work ...

    Text Solution

    |

  13. Rohan and Sunil separately can complete a work in 8 hours and 4 hours ...

    Text Solution

    |

  14. Typist A can type a report in 16 hours. Typist B can type the same rep...

    Text Solution

    |

  15. A and B can do a work in 8 days and A alone can do it in 12 days. In ...

    Text Solution

    |

  16. 24 men can do a work in 16 days while 36 women can do the same work in...

    Text Solution

    |

  17. A and B together can do a work in 24 days.B alone does its 1/3 part in...

    Text Solution

    |

  18. Ganesh, Ram and Sohan together can do a work in 16 days. If Ganesh and...

    Text Solution

    |

  19. A and B separately can complete a work in 6 days and 3 days respective...

    Text Solution

    |

  20. Ram, Dilip and Shekhar can complete a work in 20 days. If Ram and Dili...

    Text Solution

    |