Typist A can type a report in 16 hours. ...

Typist A can type a report in 16 hours. Typist B can type the same report in 20 hours and the typist C in 24 hours. All the three typists started typing at 9·00 a.m. at 1·00 p.m. the typist A stopped typing. The other two typists finished the job. Approximately at what time the report was typed ?

A

04 :10 p.m.

B

05 :11 p.m.

C

05 :45 p.m.

D

06 :15 p.m.

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished? a. 11 : 30 a.m. b. 12 noon c. 12 : 30 p.m. d. 1 p.m.

Machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print the same number of books in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished ?

In a press, there are three types of printing machines, P, Q and R. Machine P can print 10,000 pages in 8 hours, machine Q can finish the same task in 10 hours and machine R can finish the same task in 15 hours. All the three machines start the work at 9 : 00 a. m. Machine P breaks down at 11 : 00 a.m. and machines Q and R finish the task. The approximate time of completion of the job is :

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. 3 men and 4 boys do a piece of work in 8 days, while 4 men and 4 boys ...

    Text Solution

    |

  2. 8 men can dig a pit in 20 days. If a man works half as much again as a...

    Text Solution

    |

  3. If 1 man or 2 women or 3 boys can do a piece of work in 44 days, then ...

    Text Solution

    |

  4. 2 men and 3 women can finish a piece of work in 10 days, while 4 men c...

    Text Solution

    |

  5. Two men undertake to do a piece of work for Rs. 400. One alone can do ...

    Text Solution

    |

  6. 16 men and 12 women together complete a work in 20 days. If 18 women c...

    Text Solution

    |

  7. A report of 100 pages is to be typed by three typists. Typist A can ty...

    Text Solution

    |

  8. 14 workers can make 1400 toys in 5 days. One day after they started th...

    Text Solution

    |

  9. 24 boys can complete a work in 12 days while 16 men can complete the s...

    Text Solution

    |

  10. 15 men can complete a work in 10 days while 20 boys can complete the s...

    Text Solution

    |

  11. 14 men can complete a work in 12 days. 4 days after they started the w...

    Text Solution

    |

  12. 14 persons can complete a work in 16 days. 8 persons started the work ...

    Text Solution

    |

  13. Rohan and Sunil separately can complete a work in 8 hours and 4 hours ...

    Text Solution

    |

  14. Typist A can type a report in 16 hours. Typist B can type the same rep...

    Text Solution

    |

  15. A and B can do a work in 8 days and A alone can do it in 12 days. In ...

    Text Solution

    |

  16. 24 men can do a work in 16 days while 36 women can do the same work in...

    Text Solution

    |

  17. A and B together can do a work in 24 days.B alone does its 1/3 part in...

    Text Solution

    |

  18. Ganesh, Ram and Sohan together can do a work in 16 days. If Ganesh and...

    Text Solution

    |

  19. A and B separately can complete a work in 6 days and 3 days respective...

    Text Solution

    |

  20. Ram, Dilip and Shekhar can complete a work in 20 days. If Ram and Dili...

    Text Solution

    |