A and B separately can complete a work in 6 days and 3 days respectively. If they work together. Then in how many days will they complete the work ?

A

4 days

B

3 days

C

2 days

D

5 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem of how many days A and B will take to complete the work together, we can follow these steps: ### Step 1: Determine the work rates of A and B - A can complete the work in 6 days. Therefore, A's work rate is: \[ \text{Work rate of A} = \frac{1}{6} \text{ (work per day)} \] - B can complete the work in 3 days. Therefore, B's work rate is: \[ \text{Work rate of B} = \frac{1}{3} \text{ (work per day)} \] ### Step 2: Calculate the combined work rate of A and B - When A and B work together, their combined work rate is the sum of their individual work rates: \[ \text{Combined work rate} = \text{Work rate of A} + \text{Work rate of B} = \frac{1}{6} + \frac{1}{3} \] - To add these fractions, we need a common denominator. The least common multiple (LCM) of 6 and 3 is 6. Thus, we can rewrite \(\frac{1}{3}\) as \(\frac{2}{6}\): \[ \text{Combined work rate} = \frac{1}{6} + \frac{2}{6} = \frac{3}{6} = \frac{1}{2} \text{ (work per day)} \] ### Step 3: Calculate the time taken to complete the work together - If A and B together can complete \(\frac{1}{2}\) of the work in one day, then to complete the entire work (1 unit of work), the time taken is: \[ \text{Time taken} = \frac{1 \text{ (total work)}}{\frac{1}{2} \text{ (work per day)}} = 2 \text{ days} \] ### Final Answer Thus, A and B together will complete the work in **2 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. 3 men and 4 boys do a piece of work in 8 days, while 4 men and 4 boys ...

    Text Solution

    |

  2. 8 men can dig a pit in 20 days. If a man works half as much again as a...

    Text Solution

    |

  3. If 1 man or 2 women or 3 boys can do a piece of work in 44 days, then ...

    Text Solution

    |

  4. 2 men and 3 women can finish a piece of work in 10 days, while 4 men c...

    Text Solution

    |

  5. Two men undertake to do a piece of work for Rs. 400. One alone can do ...

    Text Solution

    |

  6. 16 men and 12 women together complete a work in 20 days. If 18 women c...

    Text Solution

    |

  7. A report of 100 pages is to be typed by three typists. Typist A can ty...

    Text Solution

    |

  8. 14 workers can make 1400 toys in 5 days. One day after they started th...

    Text Solution

    |

  9. 24 boys can complete a work in 12 days while 16 men can complete the s...

    Text Solution

    |

  10. 15 men can complete a work in 10 days while 20 boys can complete the s...

    Text Solution

    |

  11. 14 men can complete a work in 12 days. 4 days after they started the w...

    Text Solution

    |

  12. 14 persons can complete a work in 16 days. 8 persons started the work ...

    Text Solution

    |

  13. Rohan and Sunil separately can complete a work in 8 hours and 4 hours ...

    Text Solution

    |

  14. Typist A can type a report in 16 hours. Typist B can type the same rep...

    Text Solution

    |

  15. A and B can do a work in 8 days and A alone can do it in 12 days. In ...

    Text Solution

    |

  16. 24 men can do a work in 16 days while 36 women can do the same work in...

    Text Solution

    |

  17. A and B together can do a work in 24 days.B alone does its 1/3 part in...

    Text Solution

    |

  18. Ganesh, Ram and Sohan together can do a work in 16 days. If Ganesh and...

    Text Solution

    |

  19. A and B separately can complete a work in 6 days and 3 days respective...

    Text Solution

    |

  20. Ram, Dilip and Shekhar can complete a work in 20 days. If Ram and Dili...

    Text Solution

    |