Ram, Dilip and Shekhar can complete a wo...

Ram, Dilip and Shekhar can complete a work in 20 days. If Ram and Dilip together can complete the same work in 30 days, then how long will Shekhar take to complete it ?

A

60 days

B

62 days

C

40 days

D

56 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's denote the work done by Ram, Dilip, and Shekhar as follows: 1. **Understanding the Work Rates**: - Let the total work be represented as 1 unit of work. - Ram, Dilip, and Shekhar together can complete the work in 20 days. Therefore, their combined work rate is: \[ \text{Work rate of Ram, Dilip, and Shekhar} = \frac{1}{20} \text{ (units of work per day)} \] 2. **Calculating the Work Rate of Ram and Dilip**: - Ram and Dilip together can complete the work in 30 days. Thus, their combined work rate is: \[ \text{Work rate of Ram and Dilip} = \frac{1}{30} \text{ (units of work per day)} \] 3. **Finding Shekhar's Work Rate**: - We can find Shekhar's work rate by subtracting the work rate of Ram and Dilip from the combined work rate of Ram, Dilip, and Shekhar: \[ \text{Work rate of Shekhar} = \text{Work rate of Ram, Dilip, and Shekhar} - \text{Work rate of Ram and Dilip} \] \[ \text{Work rate of Shekhar} = \frac{1}{20} - \frac{1}{30} \] 4. **Finding a Common Denominator**: - The least common multiple (LCM) of 20 and 30 is 60. We can rewrite the fractions: \[ \frac{1}{20} = \frac{3}{60} \quad \text{and} \quad \frac{1}{30} = \frac{2}{60} \] - Therefore: \[ \text{Work rate of Shekhar} = \frac{3}{60} - \frac{2}{60} = \frac{1}{60} \] 5. **Calculating the Time Taken by Shekhar**: - If Shekhar's work rate is \(\frac{1}{60}\), it means he can complete 1 unit of work in 60 days. Thus, the time taken by Shekhar to complete the work is: \[ \text{Time taken by Shekhar} = 60 \text{ days} \] So, Shekhar will take **60 days** to complete the work.
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    UPKAR PUBLICATION |Exercise QUESTION BANK|56 Videos
  • TRAINS

    UPKAR PUBLICATION |Exercise QUESTION BANK|70 Videos

Similar Questions

Explore conceptually related problems

P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

Anil, Dinesh and Deepak together can complete a work in 40 days. Anil and Dinesh together can complete the same work in 50 days. In how many days Deepak alone can complete the same work?

Anil, Bhuvan and Chirag together can complete a work in 35 days. Anil and Chirag together can complete the same work in 60 days. In how many days Bhuvan alone can complete the same work?

Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?

UPKAR PUBLICATION -TIME AND WORK-QUESTION BANK
  1. 3 men and 4 boys do a piece of work in 8 days, while 4 men and 4 boys ...

    Text Solution

    |

  2. 8 men can dig a pit in 20 days. If a man works half as much again as a...

    Text Solution

    |

  3. If 1 man or 2 women or 3 boys can do a piece of work in 44 days, then ...

    Text Solution

    |

  4. 2 men and 3 women can finish a piece of work in 10 days, while 4 men c...

    Text Solution

    |

  5. Two men undertake to do a piece of work for Rs. 400. One alone can do ...

    Text Solution

    |

  6. 16 men and 12 women together complete a work in 20 days. If 18 women c...

    Text Solution

    |

  7. A report of 100 pages is to be typed by three typists. Typist A can ty...

    Text Solution

    |

  8. 14 workers can make 1400 toys in 5 days. One day after they started th...

    Text Solution

    |

  9. 24 boys can complete a work in 12 days while 16 men can complete the s...

    Text Solution

    |

  10. 15 men can complete a work in 10 days while 20 boys can complete the s...

    Text Solution

    |

  11. 14 men can complete a work in 12 days. 4 days after they started the w...

    Text Solution

    |

  12. 14 persons can complete a work in 16 days. 8 persons started the work ...

    Text Solution

    |

  13. Rohan and Sunil separately can complete a work in 8 hours and 4 hours ...

    Text Solution

    |

  14. Typist A can type a report in 16 hours. Typist B can type the same rep...

    Text Solution

    |

  15. A and B can do a work in 8 days and A alone can do it in 12 days. In ...

    Text Solution

    |

  16. 24 men can do a work in 16 days while 36 women can do the same work in...

    Text Solution

    |

  17. A and B together can do a work in 24 days.B alone does its 1/3 part in...

    Text Solution

    |

  18. Ganesh, Ram and Sohan together can do a work in 16 days. If Ganesh and...

    Text Solution

    |

  19. A and B separately can complete a work in 6 days and 3 days respective...

    Text Solution

    |

  20. Ram, Dilip and Shekhar can complete a work in 20 days. If Ram and Dili...

    Text Solution

    |