Home
Class 14
MATHS
A and B can complete a piece of work in ...

A and B can complete a piece of work in 8 days. B and C in 12 days while C and A in 16 days. They work together for 3 days when A leaves off. In how many days more will B and C finish the remaining work?

A

`1 1/2` days

B

`2 1/4` days

C

`7 1/8` days

D

`4 1/2` days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's denote the work done by A, B, and C in one day as \( A, B, \) and \( C \) respectively. ### Step 1: Determine the work rates of A, B, and C 1. **A + B can complete the work in 8 days.** - Work done by A and B in one day = \( \frac{1}{8} \) of the work. - Therefore, \( A + B = \frac{1}{8} \). 2. **B + C can complete the work in 12 days.** - Work done by B and C in one day = \( \frac{1}{12} \) of the work. - Therefore, \( B + C = \frac{1}{12} \). 3. **C + A can complete the work in 16 days.** - Work done by C and A in one day = \( \frac{1}{16} \) of the work. - Therefore, \( C + A = \frac{1}{16} \). ### Step 2: Set up equations We have the following equations: - \( A + B = \frac{1}{8} \) (1) - \( B + C = \frac{1}{12} \) (2) - \( C + A = \frac{1}{16} \) (3) ### Step 3: Solve the equations To find the individual work rates, we can add all three equations: \[ (A + B) + (B + C) + (C + A) = \frac{1}{8} + \frac{1}{12} + \frac{1}{16} \] This simplifies to: \[ 2A + 2B + 2C = \frac{1}{8} + \frac{1}{12} + \frac{1}{16} \] Now, we need to find a common denominator for the right side. The LCM of 8, 12, and 16 is 48. \[ \frac{1}{8} = \frac{6}{48}, \quad \frac{1}{12} = \frac{4}{48}, \quad \frac{1}{16} = \frac{3}{48} \] Adding these fractions: \[ \frac{6}{48} + \frac{4}{48} + \frac{3}{48} = \frac{13}{48} \] Thus, we have: \[ 2A + 2B + 2C = \frac{13}{48} \] Dividing by 2: \[ A + B + C = \frac{13}{96} \] ### Step 4: Find individual work rates Now we can express each worker's rate: 1. From (1): \( A = \frac{1}{8} - B \) 2. From (2): \( C = \frac{1}{12} - B \) 3. Substitute into (3): \[ \left(\frac{1}{12} - B\right) + \left(\frac{1}{8} - B\right) = \frac{1}{16} \] Solving this will give us the values of A, B, and C. ### Step 5: Calculate work done in 3 days After finding A, B, and C, we calculate the total work done by A, B, and C together in 3 days: \[ \text{Total work in 3 days} = 3 \times (A + B + C) \] ### Step 6: Calculate remaining work Subtract the work done in 3 days from the total work (which is 1 unit): \[ \text{Remaining work} = 1 - \text{Total work in 3 days} \] ### Step 7: Calculate how long B and C will take to finish the remaining work Now, we know the work done by B and C in one day: \[ \text{Work done by B and C in one day} = B + C = \frac{1}{12} \] Let \( R \) be the remaining work. The days required by B and C to finish the remaining work is: \[ \text{Days} = \frac{R}{B + C} \] ### Final Answer After calculating the above steps, we will find the number of days B and C will take to finish the remaining work.
Promotional Banner

Topper's Solved these Questions

  • MISCELLANEOUS EXERCISE -VII

    UPKAR PUBLICATION |Exercise QUESTION BANK|65 Videos
  • MISCELLANEOUS EXERCISE-VIII

    UPKAR PUBLICATION |Exercise QUESTION BANK|81 Videos

Similar Questions

Explore conceptually related problems

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

A can do a piece of work in 25 days and B can finish it in 20 days.They work together for 5 days and then A goes away.In how many days will B finish the remaining work?

A and B can do piece of work in 12 days; B and C in 15days;C and A in 20 days.In how many days will they finish it together and separately ?

UPKAR PUBLICATION -MISCELLANEOUS EXERCISE-IV-QUESTION BANK
  1. A sum of money deposited at compound interest amounts to Rs. 6690 afte...

    Text Solution

    |

  2. In an examination a student scores 4 marks for every correct answer an...

    Text Solution

    |

  3. The average of three numbers is 20. If two of the numbers are 16 and 2...

    Text Solution

    |

  4. A candidate who gets 20% marks in an examination fails by 30 marks but...

    Text Solution

    |

  5. If the L.C.M. of x and y is z , their H.C.F. is -

    Text Solution

    |

  6. Kasim can so a piece of work in 7 1/2 hours and Sunil can finish it in...

    Text Solution

    |

  7. Two numbers are in the ratio 3:4 and the product of their L.C.M and H....

    Text Solution

    |

  8. Pratap bought a radio with 25% discount on the original price. He got ...

    Text Solution

    |

  9. Four different bells ring at intervals of 5, 6, 8 and 10 minutes respe...

    Text Solution

    |

  10. The average of marks obtained by Sunil in History and Mathematics is 6...

    Text Solution

    |

  11. If a/3 = b/4 = c/7 , then the value of (a + b +c)/(c) is

    Text Solution

    |

  12. 15 persons can fill 35 boxes in 7 days. How many Persons can fill 65 b...

    Text Solution

    |

  13. A man drives 4 km distance to go around a rectangular park. If the are...

    Text Solution

    |

  14. The difference between the simple interest and the compound interest e...

    Text Solution

    |

  15. A sum of Rs. 65000 was divided into 3 parts so that they yielded the s...

    Text Solution

    |

  16. Rs. 6450 is divided between Rajan and Suresh so that for every Rs. 8 t...

    Text Solution

    |

  17. A's money is to B's money as 4:5 and B's money is to C's money as 2:3 ...

    Text Solution

    |

  18. If a man walks at 5 km/hr he reaches the bus stop 5 minutes too late a...

    Text Solution

    |

  19. In a division sum, the divisor is 12 times the quotient and 5 times...

    Text Solution

    |

  20. A and B can complete a piece of work in 8 days. B and C in 12 days whi...

    Text Solution

    |