Home
Class 14
MATHS
A can do (2)/(5) of a work in 6 days and...

A can do `(2)/(5)` of a work in 6 days and B can do `(2)/(3)` of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

A

10

B

8

C

12

D

9

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME & WORK

    GAGAN PRATAP |Exercise TIME & WORK (SHEET-2)|34 Videos
  • TIME & WORK

    GAGAN PRATAP |Exercise TIME & WORK (SHEET-3)|23 Videos
  • SURDS & INDICES

    GAGAN PRATAP |Exercise Surds & Indices (Sheet-2)|64 Videos
  • TIME SPEED & DISTANCE

    GAGAN PRATAP |Exercise MULTIPLE CHOICE QUESTIONS|143 Videos

Similar Questions

Explore conceptually related problems

A can finish 3/5 of a task in 6 days and B can finish 2/3 of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. If B and C working together will complete the same task in:

A can do (1)/(3) of a work in 30 days. B can do (2)/(5) of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

A can do 2/5 of a work in 12 days while B can do 66^(2/3)% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

A can do 4/5 of a work in 20 days and B can do 3/4 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 3/4 of the same work in:

A can do (3)/(5)th of a work in 12 days, B can do (1)/(3) rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

A can complete one-third of a work in 10 days and B can do ""_(5)^(3) th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do ""_(3)^(2) of the same work?

If A & B completed a work together in 6 days . If A completed the same work in 10 days alone . Then in how many days will B complete the same work alone ?

GAGAN PRATAP -TIME & WORK-TIME & WORK (SHEET-3)
  1. A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same...

    Text Solution

    |

  2. A and B working together can do 30% of the work in 6 days. B alone can...

    Text Solution

    |

  3. A can finish a piece of work in a certain number of days. B takes 45% ...

    Text Solution

    |

  4. A works thrice as fast as B and B works 50% more fast as C does. All t...

    Text Solution

    |

  5. A certain number of persons can complete a work in 34 days working 9 h...

    Text Solution

    |

  6. If 90 men can do a certain job in 16 days, working 12 hours day, then ...

    Text Solution

    |

  7. In a fort there was sufficient food for 760 soldiers for 44 days. Afte...

    Text Solution

    |

  8. There is sufficient food for 2400 soldiers for 60 days and each soldie...

    Text Solution

    |

  9. There is sufficient food for 4000 soldiers for 40 days and each soldie...

    Text Solution

    |

  10. A contractor undertook to finish a road in 60 days and he employ 150 m...

    Text Solution

    |

  11. 30 men working 8 hours per days can dig a pond in 16 days. By working ...

    Text Solution

    |

  12. If x men working x hours per day can do x units of work in x days, the...

    Text Solution

    |

  13. If 2 carpenters working 6 hours a day can make 460 chairs in 240 days,...

    Text Solution

    |

  14. If 6 burners burn 6 hours daily, the cost of gas for 8 days comes to R...

    Text Solution

    |

  15. If 45 persons can complete a work in 18 days, working 8 hours a day, t...

    Text Solution

    |

  16. 40 men working 8 hours a day can do a piece of work in 15 days. Find t...

    Text Solution

    |

  17. 12 men and 18 boys work 7.5 hours a day to complete any work within 60...

    Text Solution

    |

  18. A contractor undertook to finish a work in 92 days and employed 110 me...

    Text Solution

    |

  19. A contract is to be completed in 75 days and 187 men are to work 15 ho...

    Text Solution

    |

  20. A contractor employees 245 men who finish the 7/11th of total work in ...

    Text Solution

    |

  21. A contractor undertakes to make a road in 180 days of 32.8 km long and...

    Text Solution

    |