Home
Class 14
MATHS
A can do a piece of work in 10 days and ...

A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?

A

30 days

B

50 days

C

40 days

D

60 days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME & WORK

    GAGAN PRATAP |Exercise TIME & WORK (SHEET-2)|34 Videos
  • TIME & WORK

    GAGAN PRATAP |Exercise TIME & WORK (SHEET-3)|23 Videos
  • SURDS & INDICES

    GAGAN PRATAP |Exercise Surds & Indices (Sheet-2)|64 Videos
  • TIME SPEED & DISTANCE

    GAGAN PRATAP |Exercise MULTIPLE CHOICE QUESTIONS|143 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 120 days and B can do it in 150 days.The work together for 20 days.Then,B leave and A alone continues the work.12 days after that C joins A and the work.is completed in 48 days more.In how many days can C do it,if he works alone?

A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in

A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?

A alone can do a piece of work in 10 days and B alone can do it in 15 days. In how many days will A and B together do the same work?

GAGAN PRATAP -TIME & WORK-TIME & WORK (SHEET-3)
  1. A can do a piece of work in 10 days and B can do it in 12 days. They w...

    Text Solution

    |

  2. A and B working together can do 30% of the work in 6 days. B alone can...

    Text Solution

    |

  3. A can finish a piece of work in a certain number of days. B takes 45% ...

    Text Solution

    |

  4. A works thrice as fast as B and B works 50% more fast as C does. All t...

    Text Solution

    |

  5. A certain number of persons can complete a work in 34 days working 9 h...

    Text Solution

    |

  6. If 90 men can do a certain job in 16 days, working 12 hours day, then ...

    Text Solution

    |

  7. In a fort there was sufficient food for 760 soldiers for 44 days. Afte...

    Text Solution

    |

  8. There is sufficient food for 2400 soldiers for 60 days and each soldie...

    Text Solution

    |

  9. There is sufficient food for 4000 soldiers for 40 days and each soldie...

    Text Solution

    |

  10. A contractor undertook to finish a road in 60 days and he employ 150 m...

    Text Solution

    |

  11. 30 men working 8 hours per days can dig a pond in 16 days. By working ...

    Text Solution

    |

  12. If x men working x hours per day can do x units of work in x days, the...

    Text Solution

    |

  13. If 2 carpenters working 6 hours a day can make 460 chairs in 240 days,...

    Text Solution

    |

  14. If 6 burners burn 6 hours daily, the cost of gas for 8 days comes to R...

    Text Solution

    |

  15. If 45 persons can complete a work in 18 days, working 8 hours a day, t...

    Text Solution

    |

  16. 40 men working 8 hours a day can do a piece of work in 15 days. Find t...

    Text Solution

    |

  17. 12 men and 18 boys work 7.5 hours a day to complete any work within 60...

    Text Solution

    |

  18. A contractor undertook to finish a work in 92 days and employed 110 me...

    Text Solution

    |

  19. A contract is to be completed in 75 days and 187 men are to work 15 ho...

    Text Solution

    |

  20. A contractor employees 245 men who finish the 7/11th of total work in ...

    Text Solution

    |

  21. A contractor undertakes to make a road in 180 days of 32.8 km long and...

    Text Solution

    |