Home
Class 14
MATHS
A do (4)/(9)th as much work as B in (2)/...

A do `(4)/(9)`th as much work as B in `(2)/(5)`th of time. If they together take 27 days to complete a work, how much time shall B take alone to do it?

A

57

B

38

C

46

D

54

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to find out how much time B will take to complete the work alone. Let's break it down step by step. ### Step 1: Understand the relationship between A and B From the problem, we know that A does \( \frac{4}{9} \) of the work that B does in \( \frac{2}{5} \) of the time. Let’s denote: - Work done by B in 1 day = \( b \) - Work done by A in 1 day = \( a \) From the information given: \[ a = \frac{4}{9}b \] And since A takes \( \frac{2}{5} \) of the time that B takes to do the same amount of work, we can express this as: \[ \text{Time taken by A} = \frac{2}{5} \times \text{Time taken by B} \] ### Step 2: Set up the equations Let \( T_B \) be the time taken by B to complete the work alone. Then, the time taken by A is: \[ T_A = \frac{2}{5} T_B \] ### Step 3: Calculate the total work done If A and B together take 27 days to complete the work, we can express the total work done in terms of their efficiencies: \[ \text{Total Work} = (a + b) \times 27 \] ### Step 4: Substitute A's work in terms of B's work Substituting \( a = \frac{4}{9}b \) into the total work equation: \[ \text{Total Work} = \left(\frac{4}{9}b + b\right) \times 27 \] \[ = \left(\frac{4}{9}b + \frac{9}{9}b\right) \times 27 \] \[ = \left(\frac{13}{9}b\right) \times 27 \] \[ = \frac{13 \times 27}{9} b \] \[ = 39b \] ### Step 5: Calculate the individual work rates Now, we know that: - A's work rate is \( a = \frac{4}{9}b \) - B's work rate is \( b \) The total work can also be expressed in terms of B's time: \[ \text{Total Work} = b \times T_B \] ### Step 6: Equate the two expressions for total work Setting the two expressions for total work equal to each other: \[ 39b = b \times T_B \] ### Step 7: Solve for \( T_B \) Dividing both sides by \( b \) (assuming \( b \neq 0 \)): \[ 39 = T_B \] Thus, B will take **39 days** to complete the work alone. ### Final Answer B will take **39 days** to complete the work alone.
Promotional Banner

Topper's Solved these Questions

  • TIME & WORK

    GAGAN PRATAP |Exercise TIME & WORK (SHEET-2)|34 Videos
  • TIME & WORK

    GAGAN PRATAP |Exercise TIME & WORK (SHEET-3)|23 Videos
  • SURDS & INDICES

    GAGAN PRATAP |Exercise Surds & Indices (Sheet-2)|64 Videos
  • TIME SPEED & DISTANCE

    GAGAN PRATAP |Exercise MULTIPLE CHOICE QUESTIONS|143 Videos

Similar Questions

Explore conceptually related problems

A does half as much work as B in one-sixth of the time.If together they take 10 days to complete a work,how much time shall B alone take to do it?

A does half as much work as B in three-fourth of the time. If together they take 18 days to complete a work, how much time shall B take to do it alone ?

A does half as much work as B in three-fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it?

GAGAN PRATAP -TIME & WORK-TIME & WORK (SHEET-3)
  1. A do (4)/(9)th as much work as B in (2)/(5)th of time. If they togethe...

    Text Solution

    |

  2. A and B working together can do 30% of the work in 6 days. B alone can...

    Text Solution

    |

  3. A can finish a piece of work in a certain number of days. B takes 45% ...

    Text Solution

    |

  4. A works thrice as fast as B and B works 50% more fast as C does. All t...

    Text Solution

    |

  5. A certain number of persons can complete a work in 34 days working 9 h...

    Text Solution

    |

  6. If 90 men can do a certain job in 16 days, working 12 hours day, then ...

    Text Solution

    |

  7. In a fort there was sufficient food for 760 soldiers for 44 days. Afte...

    Text Solution

    |

  8. There is sufficient food for 2400 soldiers for 60 days and each soldie...

    Text Solution

    |

  9. There is sufficient food for 4000 soldiers for 40 days and each soldie...

    Text Solution

    |

  10. A contractor undertook to finish a road in 60 days and he employ 150 m...

    Text Solution

    |

  11. 30 men working 8 hours per days can dig a pond in 16 days. By working ...

    Text Solution

    |

  12. If x men working x hours per day can do x units of work in x days, the...

    Text Solution

    |

  13. If 2 carpenters working 6 hours a day can make 460 chairs in 240 days,...

    Text Solution

    |

  14. If 6 burners burn 6 hours daily, the cost of gas for 8 days comes to R...

    Text Solution

    |

  15. If 45 persons can complete a work in 18 days, working 8 hours a day, t...

    Text Solution

    |

  16. 40 men working 8 hours a day can do a piece of work in 15 days. Find t...

    Text Solution

    |

  17. 12 men and 18 boys work 7.5 hours a day to complete any work within 60...

    Text Solution

    |

  18. A contractor undertook to finish a work in 92 days and employed 110 me...

    Text Solution

    |

  19. A contract is to be completed in 75 days and 187 men are to work 15 ho...

    Text Solution

    |

  20. A contractor employees 245 men who finish the 7/11th of total work in ...

    Text Solution

    |

  21. A contractor undertakes to make a road in 180 days of 32.8 km long and...

    Text Solution

    |