A can do a piece of work in 15 days, B is 25% more efficient than A and C is 40% more efficient than B. A and C work together for 3 days and then C leaves A and B together will complete the remaining work in:
A 15 दिनों में एक कार्य करता है। B, A की तुलना में 25% अधिक कुशल है और C, B की तुलना में 40% अधिक कुशल है। A और C एक साथ 3 दिनों के लिए कार्य करते हैं और फिर C चला जाता है। A और B एक साथ मिलकर शेष कार्य को पूरा करते हैं:

A

`2(1)/(2)`days

B

`3(1)/(2)`days

C

4 days

D

3 days

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

  • TIME & WORK

    GAGAN PRATAP |Exercise TIME & WORK (SHEET-3)|23 Videos
  • TIME & WORK

    GAGAN PRATAP |Exercise TIME & WORK (SHEET-3)|23 Videos
  • SURDS & INDICES

    GAGAN PRATAP |Exercise Surds & Indices (Sheet-2)|64 Videos
  • TIME SPEED & DISTANCE

    GAGAN PRATAP |Exercise MULTIPLE CHOICE QUESTIONS|143 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

A can complete a certain work in 30 days. B is 25% more efficient than A and C is 20% more efficient than B. They all worked together for 3 days. B alone will complete the remaining work in: / A किसी निश्चित कार्य को 30 दिनों में पूरा कर सकता है | B, A की तुलना में 25% अधिक कार्य कुशल है तथा C, B की तुलना में 20% अधिक कार्य कुशल है | उन सभी ने एक साथ तीन दिनों तक कार्य किया | शेष कार्य पूरा करने में B को अकेले कितने दिन लगेंगे ?

A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?

X can do a piece of work in 25 days. Y is 25% more efficient than X. The number of days taken by Y is :

A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be completed by B alone, in: A किसी निश्चित कार्य को 40 दिनों में पूरा कर सकता है | B, A की तुलना में 25% अधिक कार्य कुशल है तथा C, B की तुलना में 22% अधिक कार्य कुशल है | वे 5 दिनों तक एक साथ कार्य करते हैं | शेष कार्य अकेले पूरा करने में B को कितने दिन लगेंगे ?

GAGAN PRATAP -TIME & WORK-TIME & WORK (SHEET-2)
  1. To complete a certain task, X is 30% more efficient than Y, and Z is 2...

    Text Solution

    |

  2. The ratio of the efficiencies of A, B, C is 7:5:4. Working togehter, t...

    Text Solution

    |

  3. A can do a piece of work in 15 days, B is 25% more efficient than A an...

    Text Solution

    |

  4. Anmol is thrice as good a workman as Vinay and therefore is able to fi...

    Text Solution

    |

  5. A can do as much work as B and C together can do. A and B can together...

    Text Solution

    |

  6. Working together, printer A and printer B would finish a task in 24 mi...

    Text Solution

    |

  7. P, Q and R three typist working simultaneously can type 456 pages in 6...

    Text Solution

    |

  8. A and B can do a piece of work in 36 days. B and C can do the same wo...

    Text Solution

    |

  9. A and B can do a piece of work in 18 days. B and C together can do it ...

    Text Solution

    |

  10. A takes three times as long as B and C together to do a job. B takes f...

    Text Solution

    |

  11. A can work 7/9 as fast as B and C together. A and B together can work ...

    Text Solution

    |

  12. A, B and C together can complete a work in 40 days. (A+B) can complete...

    Text Solution

    |

  13. A and B. working together, can complete a work in 16 days, C and A tog...

    Text Solution

    |

  14. Ram completed 60% of a task in 15 days and then takes the help of Rahi...

    Text Solution

    |

  15. B and C together takes 33(1)/(3)% more time as compared to the time ta...

    Text Solution

    |

  16. Three workers A, B and C working together completed a job in 10 days. ...

    Text Solution

    |

  17. Working together B and C take 50% more number of days than A, B and C ...

    Text Solution

    |

  18. When they work alone, B needs 25% more time to finish a job than A doe...

    Text Solution

    |

  19. A, B and C together can finish a task in 7.5 days. C is thrice as prod...

    Text Solution

    |

  20. A is thrice as productive as C. Together they can complete a job in 22...

    Text Solution

    |