Home
Class 14
MATHS
A (working alone) can complete a task in...

A (working alone) can complete a task in 'x' days. A worked alone for `6 1/2` days and was then replaced by B and C who (working together) completed the remaining task in 3 days. Working alone, B and C take '0.5x' days and 8 days respectively to complete the entire task. What is the value of x?

A

8

B

24

C

20

D

16

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will break it down step by step. ### Step 1: Define the total work Let's assume the total work is 1 unit. ### Step 2: Calculate A's work rate A can complete the entire task in 'x' days. Therefore, A's work rate is: \[ \text{Work rate of A} = \frac{1}{x} \text{ units per day} \] ### Step 3: Calculate the work done by A in 6.5 days A worked alone for \(6 \frac{1}{2}\) days, which is \(6.5\) days. The work done by A in this time is: \[ \text{Work done by A} = \text{Work rate of A} \times \text{Time} = \frac{1}{x} \times 6.5 = \frac{6.5}{x} \text{ units} \] ### Step 4: Calculate the remaining work The remaining work after A has worked for \(6.5\) days is: \[ \text{Remaining work} = 1 - \frac{6.5}{x} \] ### Step 5: Calculate the work rate of B and C B can complete the task in \(0.5x\) days, so B's work rate is: \[ \text{Work rate of B} = \frac{1}{0.5x} = \frac{2}{x} \text{ units per day} \] C can complete the task in \(8\) days, so C's work rate is: \[ \text{Work rate of C} = \frac{1}{8} \text{ units per day} \] ### Step 6: Calculate the combined work rate of B and C The combined work rate of B and C is: \[ \text{Combined work rate of B and C} = \frac{2}{x} + \frac{1}{8} \] ### Step 7: Calculate the work done by B and C in 3 days B and C completed the remaining work in \(3\) days. The work done by B and C in this time is: \[ \text{Work done by B and C} = \left(\frac{2}{x} + \frac{1}{8}\right) \times 3 \] ### Step 8: Set up the equation Since the work done by B and C is equal to the remaining work, we can set up the equation: \[ \left(\frac{2}{x} + \frac{1}{8}\right) \times 3 = 1 - \frac{6.5}{x} \] ### Step 9: Simplify the equation Distributing the \(3\) on the left side gives: \[ \frac{6}{x} + \frac{3}{8} = 1 - \frac{6.5}{x} \] Now, let's combine like terms: \[ \frac{6}{x} + \frac{6.5}{x} = 1 - \frac{3}{8} \] \[ \frac{12.5}{x} = 1 - \frac{3}{8} \] Calculating \(1 - \frac{3}{8}\): \[ 1 - \frac{3}{8} = \frac{8}{8} - \frac{3}{8} = \frac{5}{8} \] So we have: \[ \frac{12.5}{x} = \frac{5}{8} \] ### Step 10: Solve for x Cross-multiplying gives: \[ 12.5 \times 8 = 5x \] \[ 100 = 5x \] \[ x = \frac{100}{5} = 20 \] ### Final Answer The value of \(x\) is \(20\). ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?

A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

A alone can complete a task in 3 days. B alone can complete the same task in 7 days If A and B work together for 2 days, what fraction of the task will be left?

A and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?

A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

A alone can complete a task in 3 days and B alone can complete the same task in 6 days. In how manny days can A and B complete it together?