Home
Class 14
MATHS
In these question two equations numebred...

In these question two equations numebred I and numberd II are given. You have to solve both the equations and find out the correct option.
Quantity I: X, Y and Z can finish a work alone in 12,18 and 9 days respectively. X started the work and Y and Z assisted him on every 3rd day. Find the total number of days in which the work is completed.
Quantity II: A, B and C can finish a work alone in 20,12 and 15 days respectively. All three start working together. After 2 days B left the work. After 4 more days Cleft and the remaining work is completed by A alone. A worked for how many days in all?

A

`Quantity I gt quantity II`

B

`Quantity I le quantity II`

C

`Quantity I ge quantity II`

D

`Quantity I lt quantity II`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the given problem, we need to analyze both quantities step by step. ### Quantity I: **Step 1: Determine the work rates of X, Y, and Z.** - X can finish the work in 12 days, so his work rate is: \[ \text{Work rate of X} = \frac{1}{12} \text{ of the work per day} \] - Y can finish the work in 18 days, so his work rate is: \[ \text{Work rate of Y} = \frac{1}{18} \text{ of the work per day} \] - Z can finish the work in 9 days, so his work rate is: \[ \text{Work rate of Z} = \frac{1}{9} \text{ of the work per day} \] **Step 2: Find the total work done in one cycle of 3 days.** - In the first two days, only X works: \[ \text{Work done by X in 2 days} = 2 \times \frac{1}{12} = \frac{2}{12} = \frac{1}{6} \] - On the third day, X, Y, and Z work together: \[ \text{Work done on the 3rd day} = \frac{1}{12} + \frac{1}{18} + \frac{1}{9} \] To add these fractions, we find a common denominator, which is 36: \[ = \frac{3}{36} + \frac{2}{36} + \frac{4}{36} = \frac{9}{36} = \frac{1}{4} \] - Total work done in 3 days: \[ \text{Total work in 3 days} = \frac{1}{6} + \frac{1}{4} \] Finding a common denominator (12): \[ = \frac{2}{12} + \frac{3}{12} = \frac{5}{12} \] **Step 3: Determine how many cycles are needed to complete the work.** - Total work to be done = 1 (whole work) - Work done in 3 days = \(\frac{5}{12}\) Let \(n\) be the number of 3-day cycles: \[ n \times \frac{5}{12} \leq 1 \] \[ n \leq \frac{12}{5} = 2.4 \] Thus, \(n = 2\) full cycles can be completed. **Step 4: Calculate total work done after 6 days.** - Work done in 6 days: \[ 2 \times \frac{5}{12} = \frac{10}{12} = \frac{5}{6} \] **Step 5: Calculate remaining work and days needed.** - Remaining work: \[ 1 - \frac{5}{6} = \frac{1}{6} \] - On the 7th day, X works alone: \[ \text{Work done by X on 7th day} = \frac{1}{12} \] - On the 8th day, X works again: \[ \text{Work done by X on 8th day} = \frac{1}{12} \] - Total work done in the last two days: \[ \frac{1}{12} + \frac{1}{12} = \frac{2}{12} = \frac{1}{6} \] Thus, the total number of days to complete the work is: \[ 6 + 2 = 8 \text{ days} \] ### Quantity II: **Step 1: Determine the work rates of A, B, and C.** - A can finish the work in 20 days, so his work rate is: \[ \text{Work rate of A} = \frac{1}{20} \] - B can finish the work in 12 days, so his work rate is: \[ \text{Work rate of B} = \frac{1}{12} \] - C can finish the work in 15 days, so his work rate is: \[ \text{Work rate of C} = \frac{1}{15} \] **Step 2: Find the total work done in the first 2 days.** - In 2 days, A, B, and C work together: \[ \text{Work done in 2 days} = 2 \left(\frac{1}{20} + \frac{1}{12} + \frac{1}{15}\right) \] Finding a common denominator (60): \[ = 2 \left(\frac{3}{60} + \frac{5}{60} + \frac{4}{60}\right) = 2 \left(\frac{12}{60}\right) = \frac{24}{60} = \frac{2}{5} \] **Step 3: Determine remaining work after 2 days.** - Remaining work: \[ 1 - \frac{2}{5} = \frac{3}{5} \] **Step 4: Calculate work done in the next 4 days (A and C only).** - A and C work together for the next 4 days: \[ \text{Work done by A and C in 1 day} = \frac{1}{20} + \frac{1}{15} \] Finding a common denominator (60): \[ = \frac{3}{60} + \frac{4}{60} = \frac{7}{60} \] - Work done in 4 days: \[ 4 \times \frac{7}{60} = \frac{28}{60} = \frac{14}{30} = \frac{7}{15} \] **Step 5: Calculate remaining work after 6 days.** - Remaining work: \[ \frac{3}{5} - \frac{7}{15} \] Finding a common denominator (15): \[ = \frac{9}{15} - \frac{7}{15} = \frac{2}{15} \] **Step 6: Calculate how long A works alone to finish the remaining work.** - A's work rate is \(\frac{1}{20}\), so time taken to finish \(\frac{2}{15}\) work: \[ \text{Time} = \frac{\frac{2}{15}}{\frac{1}{20}} = \frac{2}{15} \times 20 = \frac{40}{15} = \frac{8}{3} \text{ days} \] **Step 7: Total days A worked.** - Total days A worked: \[ 2 \text{ (initial days)} + 4 \text{ (next days)} + \frac{8}{3} \text{ (final days)} = 6 + \frac{8}{3} = \frac{18}{3} + \frac{8}{3} = \frac{26}{3} \text{ days} \] ### Final Comparison: - Quantity I: 8 days - Quantity II: \(\frac{26}{3} \approx 8.67\) days ### Conclusion: Since \(8 < \frac{26}{3}\), we conclude that Quantity I is less than Quantity II.
Promotional Banner

Similar Questions

Explore conceptually related problems

A and B can finish a piece of work in 16 days and 12 days respectively.A started the work and worked at it for 2 days.He was then joined by B.Find the total time taken to finish the work

A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?

A, b and C can alone complete a work in 10, 12 and 15 days respectively. A and C started the work and after working for 4 days, A left and B joined. In how many days the total work was completed ?

A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.

X, Y and Z can complete a work in 15, 45 and 90 days respectively. In how many days X, Y and Z together can complete the same work?

A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

X and Y can do a piece of work in 20 days and 12 days respectively. X started line work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?