In these question two equations numebred I and numberd II are given. You have to solve both the equations and find out the correct option.
Quantity I: X, Y and Z can finish a work alone in 12,18 and 9 days respectively. X started the work and Y and Z assisted him on every 3rd day. Find the total number of days in which the work is completed.
Quantity II: A, B and C can finish a work alone in 20,12 and 15 days respectively. All three start working together. After 2 days B left the work. After 4 more days Cleft and the remaining work is completed by A alone. A worked for how many days in all?
In these question two equations numebred I and numberd II are given. You have to solve both the equations and find out the correct option.
Quantity I: X, Y and Z can finish a work alone in 12,18 and 9 days respectively. X started the work and Y and Z assisted him on every 3rd day. Find the total number of days in which the work is completed.
Quantity II: A, B and C can finish a work alone in 20,12 and 15 days respectively. All three start working together. After 2 days B left the work. After 4 more days Cleft and the remaining work is completed by A alone. A worked for how many days in all?
Quantity I: X, Y and Z can finish a work alone in 12,18 and 9 days respectively. X started the work and Y and Z assisted him on every 3rd day. Find the total number of days in which the work is completed.
Quantity II: A, B and C can finish a work alone in 20,12 and 15 days respectively. All three start working together. After 2 days B left the work. After 4 more days Cleft and the remaining work is completed by A alone. A worked for how many days in all?
A
`Quantity I gt quantity II`
B
`Quantity I le quantity II`
C
`Quantity I ge quantity II`
D
`Quantity I lt quantity II`
Text Solution
AI Generated Solution
The correct Answer is:
To solve the given problem, we need to analyze both quantities step by step.
### Quantity I:
**Step 1: Determine the work rates of X, Y, and Z.**
- X can finish the work in 12 days, so his work rate is:
\[
\text{Work rate of X} = \frac{1}{12} \text{ of the work per day}
\]
- Y can finish the work in 18 days, so his work rate is:
\[
\text{Work rate of Y} = \frac{1}{18} \text{ of the work per day}
\]
- Z can finish the work in 9 days, so his work rate is:
\[
\text{Work rate of Z} = \frac{1}{9} \text{ of the work per day}
\]
**Step 2: Find the total work done in one cycle of 3 days.**
- In the first two days, only X works:
\[
\text{Work done by X in 2 days} = 2 \times \frac{1}{12} = \frac{2}{12} = \frac{1}{6}
\]
- On the third day, X, Y, and Z work together:
\[
\text{Work done on the 3rd day} = \frac{1}{12} + \frac{1}{18} + \frac{1}{9}
\]
To add these fractions, we find a common denominator, which is 36:
\[
= \frac{3}{36} + \frac{2}{36} + \frac{4}{36} = \frac{9}{36} = \frac{1}{4}
\]
- Total work done in 3 days:
\[
\text{Total work in 3 days} = \frac{1}{6} + \frac{1}{4}
\]
Finding a common denominator (12):
\[
= \frac{2}{12} + \frac{3}{12} = \frac{5}{12}
\]
**Step 3: Determine how many cycles are needed to complete the work.**
- Total work to be done = 1 (whole work)
- Work done in 3 days = \(\frac{5}{12}\)
Let \(n\) be the number of 3-day cycles:
\[
n \times \frac{5}{12} \leq 1
\]
\[
n \leq \frac{12}{5} = 2.4
\]
Thus, \(n = 2\) full cycles can be completed.
**Step 4: Calculate total work done after 6 days.**
- Work done in 6 days:
\[
2 \times \frac{5}{12} = \frac{10}{12} = \frac{5}{6}
\]
**Step 5: Calculate remaining work and days needed.**
- Remaining work:
\[
1 - \frac{5}{6} = \frac{1}{6}
\]
- On the 7th day, X works alone:
\[
\text{Work done by X on 7th day} = \frac{1}{12}
\]
- On the 8th day, X works again:
\[
\text{Work done by X on 8th day} = \frac{1}{12}
\]
- Total work done in the last two days:
\[
\frac{1}{12} + \frac{1}{12} = \frac{2}{12} = \frac{1}{6}
\]
Thus, the total number of days to complete the work is:
\[
6 + 2 = 8 \text{ days}
\]
### Quantity II:
**Step 1: Determine the work rates of A, B, and C.**
- A can finish the work in 20 days, so his work rate is:
\[
\text{Work rate of A} = \frac{1}{20}
\]
- B can finish the work in 12 days, so his work rate is:
\[
\text{Work rate of B} = \frac{1}{12}
\]
- C can finish the work in 15 days, so his work rate is:
\[
\text{Work rate of C} = \frac{1}{15}
\]
**Step 2: Find the total work done in the first 2 days.**
- In 2 days, A, B, and C work together:
\[
\text{Work done in 2 days} = 2 \left(\frac{1}{20} + \frac{1}{12} + \frac{1}{15}\right)
\]
Finding a common denominator (60):
\[
= 2 \left(\frac{3}{60} + \frac{5}{60} + \frac{4}{60}\right) = 2 \left(\frac{12}{60}\right) = \frac{24}{60} = \frac{2}{5}
\]
**Step 3: Determine remaining work after 2 days.**
- Remaining work:
\[
1 - \frac{2}{5} = \frac{3}{5}
\]
**Step 4: Calculate work done in the next 4 days (A and C only).**
- A and C work together for the next 4 days:
\[
\text{Work done by A and C in 1 day} = \frac{1}{20} + \frac{1}{15}
\]
Finding a common denominator (60):
\[
= \frac{3}{60} + \frac{4}{60} = \frac{7}{60}
\]
- Work done in 4 days:
\[
4 \times \frac{7}{60} = \frac{28}{60} = \frac{14}{30} = \frac{7}{15}
\]
**Step 5: Calculate remaining work after 6 days.**
- Remaining work:
\[
\frac{3}{5} - \frac{7}{15}
\]
Finding a common denominator (15):
\[
= \frac{9}{15} - \frac{7}{15} = \frac{2}{15}
\]
**Step 6: Calculate how long A works alone to finish the remaining work.**
- A's work rate is \(\frac{1}{20}\), so time taken to finish \(\frac{2}{15}\) work:
\[
\text{Time} = \frac{\frac{2}{15}}{\frac{1}{20}} = \frac{2}{15} \times 20 = \frac{40}{15} = \frac{8}{3} \text{ days}
\]
**Step 7: Total days A worked.**
- Total days A worked:
\[
2 \text{ (initial days)} + 4 \text{ (next days)} + \frac{8}{3} \text{ (final days)} = 6 + \frac{8}{3} = \frac{18}{3} + \frac{8}{3} = \frac{26}{3} \text{ days}
\]
### Final Comparison:
- Quantity I: 8 days
- Quantity II: \(\frac{26}{3} \approx 8.67\) days
### Conclusion:
Since \(8 < \frac{26}{3}\), we conclude that Quantity I is less than Quantity II.
Similar Questions
Explore conceptually related problems
A and B can finish a piece of work in 16 days and 12 days respectively.A started the work and worked at it for 2 days.He was then joined by B.Find the total time taken to finish the work
A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
A, b and C can alone complete a work in 10, 12 and 15 days respectively. A and C started the work and after working for 4 days, A left and B joined. In how many days the total work was completed ?
A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
X, Y and Z can complete a work in 15, 45 and 90 days respectively. In how many days X, Y and Z together can complete the same work?
A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
X and Y can do a piece of work in 20 days and 12 days respectively. X started line work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?
Recommended Questions
- In these question two equations numebred I and numberd II are given. Y...
Text Solution
|
- X अकेले किसी काम को 40 दिनों में कार सकता है उसने 8 दिन काम कि...
Text Solution
|
- X, Y and Z can complete a piece of work in 10 days. X and Y can do it ...
Text Solution
|
- X, Y and Z can complete a piece of work in 10 days. X and Y can do it ...
Text Solution
|
- X' can complete a work in 40 days while Y is 20% more effi- cient th...
Text Solution
|
- X, Y and Z can complete a piece of work in 10 days. X and Y can do it ...
Text Solution
|
- X, Y and Z together can do a piece of work in 10 days. X alone can com...
Text Solution
|
- X does 20% of a work in a day, Y does 25% of a work in a day and X, Y ...
Text Solution
|
- X takes 3 days less than Y to finish a work. X worked alone for 4 days...
Text Solution
|