Home
Class 14
MATHS
10 men can complete project in 12 days 1...

10 men can complete project in 12 days 12 children can complete same in 16 days and 8 womwn can in 20 days 5 men and 12 children started project if after 4 days 8 children were replaced by 4 women in how many days remaining project was completed

A

(4)2/5

B

(5)1/2

C

(7)1/2

D

(6)2/3

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we need to calculate the work done by men, children, and women, and then determine how much work is left after certain days. ### Step 1: Calculate the total work in terms of man-days - **10 men can complete the project in 12 days.** - Total work = 10 men × 12 days = 120 man-days. ### Step 2: Calculate the work done by 5 men and 12 children in 4 days - **12 children can complete the project in 16 days.** - Total work = 12 children × 16 days = 192 child-days. - Work done by 1 child in 1 day = 1/192 of the project. - **Work done by 5 men in 1 day:** - Work done by 1 man in 1 day = 1/120 of the project. - Work done by 5 men in 1 day = 5 × (1/120) = 5/120 = 1/24 of the project. - **Work done by 12 children in 1 day:** - Work done by 12 children in 1 day = 12 × (1/192) = 12/192 = 1/16 of the project. - **Total work done by 5 men and 12 children in 1 day:** - Total work in 1 day = (1/24) + (1/16). - To add these fractions, find a common denominator (48): - (1/24) = 2/48 - (1/16) = 3/48 - Total work in 1 day = 2/48 + 3/48 = 5/48 of the project. - **Work done in 4 days:** - Work done in 4 days = 4 × (5/48) = 20/48 = 5/12 of the project. ### Step 3: Calculate the remaining work - **Remaining work = Total work - Work done in 4 days** - Remaining work = 1 - 5/12 = 7/12 of the project. ### Step 4: Calculate the new team composition after 4 days - After 4 days, 8 children are replaced by 4 women. - **Work done by 4 women:** - **8 women can complete the project in 20 days.** - Total work = 8 women × 20 days = 160 woman-days. - Work done by 1 woman in 1 day = 1/160 of the project. - Work done by 4 women in 1 day = 4 × (1/160) = 4/160 = 1/40 of the project. - **Work done by 4 children:** - Work done by 4 children in 1 day = 4 × (1/192) = 4/192 = 1/48 of the project. - **Total work done by 4 women and 4 children in 1 day:** - Total work in 1 day = (1/40) + (1/48). - Find a common denominator (240): - (1/40) = 6/240 - (1/48) = 5/240 - Total work in 1 day = 6/240 + 5/240 = 11/240 of the project. ### Step 5: Calculate the time required to complete the remaining work - **Remaining work = 7/12 of the project.** - **Time required = Remaining work / Work done in 1 day** - Time required = (7/12) ÷ (11/240) = (7/12) × (240/11) = (7 × 20) / 11 = 140/11 days. ### Final Answer: The remaining project was completed in approximately **12.73 days** (or 12 days and 16 hours).
Promotional Banner

Similar Questions

Explore conceptually related problems

12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

12 men can finish a project in 20 days. 18 women can finish the same project in 16 days and 24 children can finish it in 18 days. 8 women and 16 children worked for 9 days and then left. In how many will 10 men coplete the remaining project ?

6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined

If 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?

8 men can do a work in 12 days while 20 women can do it in 10 days. In how many days can 12 men and 15 women complete the same work.

4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?