Home
Class 14
MATHS
A alone can complete a task in 10 days A...

A alone can complete a task in 10 days A,B worked together for 3 days after which C replaced B. A was `50%` more efficient than C, After A and C had worked for three days, `13%` task was incomplete. In approximately how many days B (working alone) can complete the entire work?

A

24

B

64

C

12

D

43

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will break down the information given and calculate the required values. ### Step 1: Determine A's efficiency A can complete the task in 10 days. Therefore, A's work done in one day is: \[ \text{Work done by A in 1 day} = \frac{1}{10} \] ### Step 2: Determine C's efficiency It is given that A is 50% more efficient than C. If we denote C's efficiency as \( x \), then: \[ A = 1.5 \times C \implies \frac{1}{10} = 1.5x \implies x = \frac{1}{15} \] Thus, C can complete the task in 15 days. ### Step 3: Determine B's efficiency Let B's efficiency be \( y \). Since we do not know B's efficiency yet, we will keep it as \( \frac{1}{y} \). ### Step 4: Calculate the work done by A and B together in 3 days In 3 days, the work done by A and B together is: \[ \text{Work done by A in 3 days} = 3 \times \frac{1}{10} = \frac{3}{10} \] The work done by B in 3 days is: \[ \text{Work done by B in 3 days} = 3 \times \frac{1}{y} = \frac{3}{y} \] Thus, the total work done by A and B together in 3 days is: \[ \text{Total work in 3 days} = \frac{3}{10} + \frac{3}{y} \] ### Step 5: Calculate the work done by A and C together in the next 3 days After 3 days, C replaces B, and A and C work together for another 3 days. The work done by A and C in 3 days is: \[ \text{Work done by A in 3 days} = 3 \times \frac{1}{10} = \frac{3}{10} \] \[ \text{Work done by C in 3 days} = 3 \times \frac{1}{15} = \frac{1}{5} \] Thus, the total work done by A and C together in 3 days is: \[ \text{Total work in 3 days} = \frac{3}{10} + \frac{1}{5} = \frac{3}{10} + \frac{2}{10} = \frac{5}{10} = \frac{1}{2} \] ### Step 6: Calculate total work done and remaining work The total work done by A and B in the first 3 days and A and C in the next 3 days is: \[ \text{Total work done} = \left(\frac{3}{10} + \frac{3}{y}\right) + \frac{1}{2} \] We know that 13% of the task is incomplete, meaning 87% of the task is complete. Therefore: \[ \left(\frac{3}{10} + \frac{3}{y}\right) + \frac{1}{2} = \frac{87}{100} \] ### Step 7: Solve for B's efficiency Convert all fractions to a common denominator: \[ \frac{3}{10} = \frac{30}{100}, \quad \frac{1}{2} = \frac{50}{100} \] Thus, we have: \[ \frac{30}{100} + \frac{3}{y} + \frac{50}{100} = \frac{87}{100} \] This simplifies to: \[ \frac{80}{100} + \frac{3}{y} = \frac{87}{100} \] Subtracting \( \frac{80}{100} \) from both sides gives: \[ \frac{3}{y} = \frac{7}{100} \] Cross-multiplying gives: \[ 3 \times 100 = 7y \implies 300 = 7y \implies y = \frac{300}{7} \approx 42.86 \] ### Step 8: Conclusion Thus, B can complete the entire work alone in approximately 43 days.
Promotional Banner

Similar Questions

Explore conceptually related problems

A is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?

A and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?