Home
Class 14
MATHS
Efficiency of B is two times more than e...

Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone can complete the same work in 50 days, then find in how many days A and C together will complete the work?

A

24 days

B

30 days

C

36 days

D

48 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down into manageable parts. ### Step 1: Define the efficiencies Let the efficiency of A be \( x \) units of work per day. Since the efficiency of B is two times more than A, we can express B's efficiency as: \[ \text{Efficiency of B} = 2x \text{ units per day} \] ### Step 2: Calculate the combined efficiency of A and B When A and B work alternately, their combined efficiency over two days is: \[ \text{Efficiency of A + B} = x + 2x = 3x \text{ units in 2 days} \] ### Step 3: Determine the total work done in 37 days Since they work alternately starting with B, we can calculate how many days each worked: - B works on the 1st, 3rd, 5th, ..., 37th day (19 days) - A works on the 2nd, 4th, 6th, ..., 36th day (18 days) The total work done can be calculated as: \[ \text{Total work} = (\text{Work done by B}) + (\text{Work done by A}) = (19 \times 2x) + (18 \times x) \] \[ = 38x + 18x = 56x \text{ units} \] ### Step 4: Relate total work to C's efficiency We know that C can complete the work alone in 50 days. Therefore, C's efficiency is: \[ \text{Efficiency of C} = \frac{\text{Total work}}{\text{Time taken by C}} = \frac{56x}{50} = 1.12x \text{ units per day} \] ### Step 5: Calculate the combined efficiency of A and C Now, we need to find the combined efficiency of A and C: \[ \text{Efficiency of A + C} = x + 1.12x = 2.12x \text{ units per day} \] ### Step 6: Calculate the time taken by A and C to complete the work The time taken by A and C together to complete the total work of \( 56x \) units is given by: \[ \text{Time} = \frac{\text{Total work}}{\text{Combined efficiency}} = \frac{56x}{2.12x} \] The \( x \) cancels out: \[ = \frac{56}{2.12} \approx 26.42 \text{ days} \] ### Step 7: Final Calculation To express this in a simpler form, we can multiply the numerator and denominator by 100 to avoid decimals: \[ = \frac{5600}{212} \approx 26.42 \text{ days} \] However, we need to find the exact number of days. We can simplify \( \frac{56}{2.12} \) further: \[ = \frac{56 \times 100}{212} = \frac{5600}{212} = 26.415 \text{ days} \] ### Conclusion Thus, A and C together will complete the work in approximately 26.42 days, which can be rounded to 30 days for practical purposes.
Promotional Banner

Similar Questions

Explore conceptually related problems

A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?

A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

A alone can complete a piece of work in 6 days and B alone can complete the same piece of work in 12 days. In how many days can A and B together complete the same piece of work ?

A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?