Home
Class 14
MATHS
7 men and 6 women together can complete ...

7 men and 6 women together can complete a piece of work in 8 days and work done by a women in one day is half the work done by a man in one day. If 8 men and 4 women started working and after 3 days 4 men left the work and 4 new women joined them, in how many more days will the remaining work be completed?

A

7 days

B

6 days

C

5.25 days

D

6.25 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the work done by men and women Given: - 7 men and 6 women can complete the work in 8 days. - The work done by a woman in one day is half the work done by a man in one day. Let the work done by one man in one day be \(2x\) (units of work). Then, the work done by one woman in one day is \(x\). ### Step 2: Calculate total work The total work done by 7 men and 6 women in one day is: \[ \text{Work per day} = 7 \times 2x + 6 \times x = 14x + 6x = 20x \] Since they complete the work in 8 days, the total work \(W\) is: \[ W = \text{Work per day} \times \text{Number of days} = 20x \times 8 = 160x \] ### Step 3: Work done in the first 3 days Now, 8 men and 4 women start working. The work done by them in one day is: \[ \text{Work per day} = 8 \times 2x + 4 \times x = 16x + 4x = 20x \] In 3 days, the total work done is: \[ \text{Total work done in 3 days} = 20x \times 3 = 60x \] ### Step 4: Calculate remaining work The remaining work after 3 days is: \[ \text{Remaining work} = \text{Total work} - \text{Work done in 3 days} = 160x - 60x = 100x \] ### Step 5: Work after 3 days After 3 days, 4 men leave, and 4 new women join. Now, the workforce consists of: - Remaining men: \(8 - 4 = 4\) - New women: \(4 + 4 = 8\) The work done by the remaining workers in one day is: \[ \text{Work per day} = 4 \times 2x + 8 \times x = 8x + 8x = 16x \] ### Step 6: Calculate days required to finish remaining work To find the number of days required to complete the remaining work of \(100x\): \[ \text{Days required} = \frac{\text{Remaining work}}{\text{Work per day}} = \frac{100x}{16x} = \frac{100}{16} = 6.25 \text{ days} \] ### Final Answer The remaining work will be completed in **6.25 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed

8 men and 4 woment together can complete a piece ot work in 6 days. Work done by a man in one day is double the work done by a women in one day 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined the work. Quantity I: more days required to complete the work II: 5 days

10 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?

Three men or five women can complete a piece of work in 8 days. In how many days can 6 men and 6 women complete it?