Home
Class 14
MATHS
'A' can complete a work in 20 days while...

'A' can complete a work in 20 days while B is `25%` more efficient than A. B worked for 6 days and left. The remaining work is completed by Cin 15 days. Find in how many days C can complete the whole work alone.

A

27 days

B

21 days

C

18 days

D

24 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how many days C can complete the whole work alone. Let's break down the solution step by step. ### Step 1: Determine A's work rate A can complete the work in 20 days. Therefore, A's work rate is: \[ \text{Work rate of A} = \frac{1}{20} \text{ (work per day)} \] ### Step 2: Determine B's work rate B is 25% more efficient than A. To find B's work rate, we first calculate 25% of A's work rate: \[ 25\% \text{ of A's work rate} = 0.25 \times \frac{1}{20} = \frac{1}{80} \] Now, we add this to A's work rate to find B's work rate: \[ \text{Work rate of B} = \frac{1}{20} + \frac{1}{80} \] To add these fractions, we need a common denominator, which is 80: \[ \text{Work rate of B} = \frac{4}{80} + \frac{1}{80} = \frac{5}{80} = \frac{1}{16} \text{ (work per day)} \] ### Step 3: Calculate the work done by B in 6 days Now, we calculate how much work B completes in 6 days: \[ \text{Work done by B in 6 days} = 6 \times \frac{1}{16} = \frac{6}{16} = \frac{3}{8} \] ### Step 4: Determine the remaining work The total work is considered as 1 unit. Therefore, the remaining work after B has worked for 6 days is: \[ \text{Remaining work} = 1 - \frac{3}{8} = \frac{5}{8} \] ### Step 5: Calculate C's work rate C completes the remaining work in 15 days. Therefore, C's work rate can be calculated as: \[ \text{Work rate of C} = \frac{\text{Remaining work}}{\text{Time taken by C}} = \frac{\frac{5}{8}}{15} = \frac{5}{120} = \frac{1}{24} \text{ (work per day)} \] ### Step 6: Determine how many days C can complete the whole work alone To find out how many days C can complete the whole work alone, we take the reciprocal of C's work rate: \[ \text{Days taken by C to complete the whole work} = \frac{1}{\frac{1}{24}} = 24 \text{ days} \] ### Final Answer C can complete the whole work alone in **24 days**.
Promotional Banner

Similar Questions

Explore conceptually related problems

A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?

A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?