Home
Class 14
MATHS
If a man completes 3/7 work in 6 days , ...

If a man completes `3/7` work in 6 days , then how many more days will be require for completing the remaining work ?

A

8

B

14

C

9

D

7

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these instructions: ### Step 1: Understand the total work done The man completes \( \frac{3}{7} \) of the work in 6 days. ### Step 2: Determine the total work Let the total work be represented as \( 7x \). This means that \( \frac{3}{7} \) of the total work is \( 3x \). ### Step 3: Calculate the remaining work The remaining work can be calculated as: \[ \text{Remaining work} = \text{Total work} - \text{Work done} = 7x - 3x = 4x \] ### Step 4: Find the rate of work Since the man completes \( 3x \) in 6 days, we can find the rate of work per day: \[ \text{Rate of work} = \frac{3x}{6} = \frac{x}{2} \text{ (work per day)} \] ### Step 5: Calculate the time required to complete the remaining work To find out how many days it will take to complete the remaining work \( 4x \): \[ \text{Days required} = \frac{\text{Remaining work}}{\text{Rate of work}} = \frac{4x}{\frac{x}{2}} = 4x \times \frac{2}{x} = 8 \text{ days} \] ### Conclusion Thus, the man will require **8 more days** to complete the remaining work. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A works thrice as much as B. If A can complete this work in 12 days, then in how many days will both A and B complete this work ?