Home
Class 14
MATHS
Twenty persons take 15 days to complete ...

Twenty persons take 15 days to complete a certain work, working 8 hours a day. To complete the same work in 4 days. working 10 hours a day. the number of persons required is:

A

75

B

60

C

80

D

55

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to use the concept of work, which can be expressed in terms of the number of persons (M), the number of days (D), and the number of hours worked per day (H). The formula we will use is: \[ M_1 \times D_1 \times H_1 = M_2 \times D_2 \times H_2 \] Where: - \( M_1 \) = Initial number of persons - \( D_1 \) = Initial number of days - \( H_1 \) = Initial hours per day - \( M_2 \) = Required number of persons - \( D_2 \) = Required number of days - \( H_2 \) = Required hours per day ### Step-by-Step Solution 1. **Identify the given values**: - \( M_1 = 20 \) persons - \( D_1 = 15 \) days - \( H_1 = 8 \) hours/day - \( D_2 = 4 \) days - \( H_2 = 10 \) hours/day 2. **Substitute the values into the formula**: \[ 20 \times 15 \times 8 = M_2 \times 4 \times 10 \] 3. **Calculate the left side of the equation**: \[ 20 \times 15 = 300 \] \[ 300 \times 8 = 2400 \] So, the left side equals 2400. 4. **Set up the equation**: \[ 2400 = M_2 \times 4 \times 10 \] 5. **Calculate the right side**: \[ 4 \times 10 = 40 \] So, we have: \[ 2400 = M_2 \times 40 \] 6. **Solve for \( M_2 \)**: \[ M_2 = \frac{2400}{40} \] \[ M_2 = 60 \] Thus, the number of persons required to complete the work in 4 days, working 10 hours a day, is **60 persons**.
Promotional Banner

Similar Questions

Explore conceptually related problems

12 men working 8 hours per day complete a piece of work in 10 days.To complete the same work in 8 days,working 15 hours a day, the number of men required is a.4 b.5 c.6 d.8

Working 5 hours a day. A can' complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in

24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?

Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5 5/(11) b. 5 6/(11) c. 6 6/(11) d. 6 6/(11)