Home
Class 14
MATHS
A and B can complete a work in 12 days a...

A and B can complete a work in 12 days and 20 days, respectively They work together for 4 days. C alone completes the remaining work in 14 days. B and C together can complete the same work in:

A

16 days

B

12 days

C

15 days

D

10 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these calculations: ### Step 1: Determine the work rates of A and B - A can complete the work in 12 days. Therefore, A's work rate is: \[ \text{Work rate of A} = \frac{1}{12} \text{ (work per day)} \] - B can complete the work in 20 days. Therefore, B's work rate is: \[ \text{Work rate of B} = \frac{1}{20} \text{ (work per day)} \] ### Step 2: Calculate the combined work rate of A and B - The combined work rate of A and B when they work together is: \[ \text{Combined work rate of A and B} = \frac{1}{12} + \frac{1}{20} \] - To add these fractions, we find a common denominator, which is 60: \[ \frac{1}{12} = \frac{5}{60}, \quad \frac{1}{20} = \frac{3}{60} \] - Therefore, \[ \text{Combined work rate of A and B} = \frac{5}{60} + \frac{3}{60} = \frac{8}{60} = \frac{2}{15} \text{ (work per day)} \] ### Step 3: Calculate the work done by A and B in 4 days - In 4 days, the amount of work done by A and B together is: \[ \text{Work done in 4 days} = 4 \times \frac{2}{15} = \frac{8}{15} \] ### Step 4: Determine the remaining work - The total work can be considered as 1 (or 60 units for easier calculation). The remaining work after A and B have worked for 4 days is: \[ \text{Remaining work} = 1 - \frac{8}{15} = \frac{15}{15} - \frac{8}{15} = \frac{7}{15} \] ### Step 5: Calculate C's work rate - C completes the remaining work in 14 days. Therefore, C's work rate is: \[ \text{Work rate of C} = \frac{\frac{7}{15}}{14} = \frac{7}{15 \times 14} = \frac{7}{210} = \frac{1}{30} \text{ (work per day)} \] ### Step 6: Calculate the combined work rate of B and C - Now we find the combined work rate of B and C: \[ \text{Combined work rate of B and C} = \text{Work rate of B} + \text{Work rate of C} = \frac{1}{20} + \frac{1}{30} \] - To add these fractions, we find a common denominator, which is 60: \[ \frac{1}{20} = \frac{3}{60}, \quad \frac{1}{30} = \frac{2}{60} \] - Therefore, \[ \text{Combined work rate of B and C} = \frac{3}{60} + \frac{2}{60} = \frac{5}{60} = \frac{1}{12} \text{ (work per day)} \] ### Step 7: Calculate the time taken by B and C to complete the work - The time taken by B and C to complete the entire work (1 unit) is: \[ \text{Time} = \frac{1}{\text{Combined work rate of B and C}} = \frac{1}{\frac{1}{12}} = 12 \text{ days} \] ### Final Answer B and C together can complete the work in **12 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do 4/5 of a work in 20 days and B can do 3/4 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 3/4 of the same work in:

A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

A can do (1)/(3) of a work in 30 days. B can do (2)/(5) of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?