Home
Class 14
MATHS
Vijay and Sahil together complete a piec...

Vijay and Sahil together complete a piece of work in 40 days, Sahil and Ranjit can complete the same work in 48 days and Ranjit and Vijay can complete the same work in 60 days. In how many days can all the three complete the same work while working together?

A

16

B

24

C

32

D

38

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to find out how many days Vijay, Sahil, and Ranjit can complete the work together. We will use the concept of work rates. 1. **Define Work Rates**: Let the work rates of Vijay, Sahil, and Ranjit be \( V \), \( S \), and \( R \) respectively. The work done is inversely proportional to the time taken. 2. **Set Up Equations**: From the information given: - Vijay and Sahil together complete the work in 40 days: \[ V + S = \frac{1}{40} \quad \text{(Equation 1)} \] - Sahil and Ranjit together complete the work in 48 days: \[ S + R = \frac{1}{48} \quad \text{(Equation 2)} \] - Ranjit and Vijay together complete the work in 60 days: \[ R + V = \frac{1}{60} \quad \text{(Equation 3)} \] 3. **Add the Equations**: Now, we will add all three equations: \[ (V + S) + (S + R) + (R + V) = \frac{1}{40} + \frac{1}{48} + \frac{1}{60} \] This simplifies to: \[ 2V + 2S + 2R = \frac{1}{40} + \frac{1}{48} + \frac{1}{60} \] Dividing the entire equation by 2: \[ V + S + R = \frac{1}{2} \left( \frac{1}{40} + \frac{1}{48} + \frac{1}{60} \right) \] 4. **Calculate the Right Side**: We need to find a common denominator for \( 40, 48, \) and \( 60 \). The LCM of these numbers is \( 240 \). \[ \frac{1}{40} = \frac{6}{240}, \quad \frac{1}{48} = \frac{5}{240}, \quad \frac{1}{60} = \frac{4}{240} \] Adding these fractions: \[ \frac{6}{240} + \frac{5}{240} + \frac{4}{240} = \frac{15}{240} = \frac{1}{16} \] 5. **Substituting Back**: Now substituting back into our equation: \[ V + S + R = \frac{1}{2} \left( \frac{1}{16} \right) = \frac{1}{32} \] 6. **Conclusion**: Therefore, the time taken by all three working together to complete the work is: \[ \text{Time} = \frac{1}{V + S + R} = \frac{1}{\frac{1}{32}} = 32 \text{ days} \] **Final Answer**: Vijay, Sahil, and Ranjit together can complete the work in **32 days**.
Promotional Banner

Similar Questions

Explore conceptually related problems

A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

C alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?

If 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?

A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?

Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?